321 N LAUREL AVE 90048

Certificate Information: 321 N LAUREL AVE 90048

Application / Permit
19014-30000-05874
Plan Check / Job No.
B19WL06047
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Rear addition to existing SFD and interior remodel. Per engineering design.
Permit Issued
Issued on 11/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/29/2019 MANUEL GARCIA
Corrections Issued 10/29/2019 MANUEL GARCIA
Plan Check Approved 10/30/2019 ALFREDO JARA
Issued 11/8/2019 LADBS
CofO in Progress 10/22/2020 CHRIS CHRISTENSEN
Permit Finaled 10/26/2020 DEROLD HAUFF
CofO Issued 10/26/2020 DEROLD HAUFF
Permit Finaled 10/26/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/30/2019 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/30/2019 ANTHONY MAINEZ
Sewer availability Cleared 10/30/2019 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2020 Corrections Issued HORACE FULTZ
Excavation/Setback/Form/Re-Bar 1/30/2020 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 2/10/2020 Partial Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Approved FREDDIE RIVERA
Wood Frame 2/27/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/22/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/22/2020 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 6/22/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 6/22/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 6/22/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/22/2020 Approved CHRIS CHRISTENSEN
Insulation 7/1/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/1/2020 Approved CHRIS CHRISTENSEN
Shower Pan 7/1/2020 Approved CHRIS CHRISTENSEN
Wood Frame 7/1/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/7/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/7/2020 Approved CHRIS CHRISTENSEN
Special/Order Compliance 9/2/2020 Approved CHRIS CHRISTENSEN
Special/Order Compliance 9/16/2020 Approved CHRIS CHRISTENSEN
Special/Order Compliance 10/7/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/21/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/21/2020 Approved CHRIS CHRISTENSEN
Final 10/21/2020 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/21/2020 Approved CHRIS CHRISTENSEN
Green Building Final 10/21/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 10/21/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 10/21/2020 Approved CHRIS CHRISTENSEN
METHANE-Final 10/21/2020 Approved CHRIS CHRISTENSEN
METHANE-Rough 10/21/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/21/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/21/2020 Approved CHRIS CHRISTENSEN