1058 E MARCO PL 90291
Certificate Information: 1058 E MARCO PL 90291
- Application / Permit
- 19014-30000-05817
- Plan Check / Job No.
- B19WL05996
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and interior remodel to an existing SFD.
- Permit Issued
- Issued on 2/19/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | KAVIAN REFAHI |
| Corrections Issued | 11/14/2019 | KAVIAN REFAHI |
| Quality Review Completed | 11/22/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Applicant returned to address corrections | 1/22/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/4/2020 | KAVIAN REFAHI |
| Plan Check Approved | 2/10/2020 | KAVIAN REFAHI |
| Issued | 2/19/2020 | LADBS |
| CofO in Progress | 10/22/2021 | DAVID FEILER |
| Permit Finaled | 10/28/2021 | DANIEL ORRANTE |
| CofO Issued | 10/28/2021 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 1/15/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| ZA Case | Cleared | 1/15/2020 | NOAH MCCOY |
| Green Code | Cleared | 1/21/2020 | RICHARD GARCIA |
Contact Information
| Architect | , ; Lic. No.: C34881 | 315 WASHINGTON BLVD SUITE 2 VENICE BEACH, CA 90292 |
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | DAVID HEINE |
| Deputy Drilled-In Anchors | 4/9/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 4/9/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | DAVID HEINE |
| Green Building Rough | 4/10/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 4/14/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 6/19/2020 | Corrections Issued | DAVID HEINE |
| PLUMBING-Rough | 7/17/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 7/20/2020 | Approved | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2020 | Partial Approval | DAVID HEINE |
| HVAC-Rough | 7/20/2020 | Partial Approval | DAVID HEINE |
| HVAC-Rough | 8/5/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 8/5/2020 | Partial Approval | DAVID HEINE |
| Wood Frame | 8/6/2020 | Approved | DAVID HEINE |
| Insulation | 8/10/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 8/21/2020 | Approved | DAVID HEINE |
| Gas Test | 12/23/2020 | Approved | DAVID HEINE |
| Final | 6/10/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 6/10/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 6/10/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 7/9/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 7/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/21/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 9/21/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/13/2021 | Not Ready for Inspection | DAVID FEILER |
| Final | 10/22/2021 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 10/22/2021 | Approved | DAVID FEILER |