4060 S ALLA ROAD 90066

Certificate Information: 4060 S ALLA ROAD 90066

Application / Permit
19014-30000-05816
Plan Check / Job No.
B19WL05994
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition (327 SF) and remodel to (e) SFD
Permit Issued
Issued on 1/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/25/2019 REZA HAGHIGHAT
Corrections Issued 11/5/2019 REZA HAGHIGHAT
Plan Check Approved 11/5/2019 VLADIMIR ARUTYUNYAN
Issued 1/24/2020 LADBS
CofO in Progress 8/29/2023 JESUS RODRIGUEZ
Permit Finaled 9/6/2023 DANIEL ORRANTE
CofO Issued 9/6/2023 DANIEL ORRANTE
Permit Finaled 9/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2019 JOSE CRUZ RODRIGUEZ
Roof/Waste drainage to street Cleared 10/25/2019 JOSE CRUZ RODRIGUEZ

Contact Information

Architect , ; Lic. No.: C34881 315 WASHINGTON BLVD SUITE 2      VENICE BEACH, CA 90292
Contractor Casa Blanca Construction; Lic. No.: 608139-B 1219 W R STREET      WILMINGTON, CA 90744
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/12/2020 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 2/14/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 3/2/2020 Partial Approval KENNETH NAGLE
Insulation 3/2/2020 Partial Approval KENNETH NAGLE
Deputy Wood Construction 4/7/2020 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Partial Approval JUAN VALENZUELA
HVAC-Rough 4/9/2020 Corrections Issued JUAN VALENZUELA
HVAC-Rough 4/17/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/17/2020 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 4/23/2020 Partial Inspection DAVID FEILER
HVAC-Rough 4/23/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/23/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 4/24/2020 Approved DAVID FEILER
Green Building Rough 4/24/2020 Approved DAVID FEILER
Interior/Exterior Lathing 4/24/2020 Partial Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 4/24/2020 Approved DAVID FEILER
Shower Pan 4/24/2020 Approved DAVID FEILER
Insulation 4/28/2020 Approved DAVID FEILER
Drywall Nailing 5/1/2020 Approved DAVID FEILER
Interior/Exterior Lathing 5/1/2020 Approved DAVID FEILER
ELECTRICAL-Final 7/21/2020 Approved DAVID HEINE
HVAC-Final 7/21/2020 Approved DAVID HEINE
PLUMBING-Final 7/21/2020 Approved DAVID HEINE
Final 8/11/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 8/11/2022 Approved JESUS RODRIGUEZ
Green Building Final 8/11/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 8/11/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/22/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 9/22/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 9/22/2022 Approved JESUS RODRIGUEZ
Final 8/28/2023 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved JESUS RODRIGUEZ