3455 S MCLAUGHLIN AVE 90066
Certificate Information: 3455 S MCLAUGHLIN AVE 90066
- Application / Permit
- 19014-30000-05785
- Plan Check / Job No.
- B19WL05959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SECOND STORY ADDITION TO (E) GARAGE TO CREATE (N) ADU PER AB494 AND SB229.
- Permit Issued
- Issued on 5/18/2020
- Issuing Office
- Current Status
- CofO Issued on 4/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Green Plans Picked Up | 1/6/2019 | APPLICANT |
| Submitted | 10/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | KAVIAN REFAHI |
| Corrections Issued | 12/2/2019 | KAVIAN REFAHI |
| Quality Review Completed | 12/11/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/31/2020 | KAVIAN REFAHI |
| Plan Check Approved | 4/21/2020 | KAVIAN REFAHI |
| Issued | 5/18/2020 | APPLICANT |
| Building Plans Picked Up | 6/5/2020 | APPLICANT |
| CofO in Progress | 4/27/2021 | KENNETH NAGLE |
| Permit Finaled | 4/27/2021 | KENNETH NAGLE |
| CofO Issued | 4/27/2021 | KENNETH NAGLE |
| Permit Finaled | 4/27/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/2/2019 | KAVIAN REFAHI |
| Address approval | Cleared | 2/25/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | DINAH GARIN |
| Sewer availability | Cleared | 2/25/2020 | DINAH GARIN |
| Green Code | Cleared | 3/31/2020 | RICHARD GARCIA |
| ZA Case | Cleared | 4/3/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/3/2020 | MAXFIELD VERMY |
| Construction near power lines | Cleared | 4/8/2020 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 5/4/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2020 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 9/23/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Conditional Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 10/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 10/22/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| Sewer | 10/27/2020 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 10/27/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/29/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 10/29/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 10/29/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/29/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/5/2020 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 11/5/2020 | Corrections Issued | KENNETH NAGLE |
| Green Building Rough | 11/5/2020 | Approved | KENNETH NAGLE |
| HVAC-Rough | 11/5/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 11/5/2020 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 11/13/2020 | Approved | RICHARD ROBLES |
| ELECTRICAL-Rough | 11/13/2020 | Approved | RICHARD ROBLES |
| Insulation | 11/23/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 12/1/2020 | Approved | RICHARD ROBLES |
| ELECTRICAL-Final | 12/4/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Gas Test | 12/4/2020 | Approved | RICHARD ROBLES |
| Shower Pan | 12/4/2020 | Approved | RICHARD ROBLES |
| Underground Mechanical | 12/4/2020 | Approved | RICHARD ROBLES |
| ELECTRICAL-Final | 3/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 3/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/16/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 3/16/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/16/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/16/2021 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/22/2021 | Corrections Issued | EVAN COOPER |
| Final | 4/5/2021 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | EVAN COOPER |
| Final | 4/13/2021 | Conditional Approval | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | KENNETH NAGLE |