3455 S MCLAUGHLIN AVE 90066

Certificate Information: 3455 S MCLAUGHLIN AVE 90066

Application / Permit
19014-30000-05785
Plan Check / Job No.
B19WL05959
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SECOND STORY ADDITION TO (E) GARAGE TO CREATE (N) ADU PER AB494 AND SB229.
Permit Issued
Issued on 5/18/2020
Issuing Office
Current Status
CofO Issued on 4/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Green Plans Picked Up 1/6/2019 APPLICANT
Submitted 10/24/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 KAVIAN REFAHI
Corrections Issued 12/2/2019 KAVIAN REFAHI
Quality Review Completed 12/11/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/31/2020 KAVIAN REFAHI
Plan Check Approved 4/21/2020 KAVIAN REFAHI
Issued 5/18/2020 APPLICANT
Building Plans Picked Up 6/5/2020 APPLICANT
CofO in Progress 4/27/2021 KENNETH NAGLE
Permit Finaled 4/27/2021 KENNETH NAGLE
CofO Issued 4/27/2021 KENNETH NAGLE
Permit Finaled 4/27/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/2/2019 KAVIAN REFAHI
Address approval Cleared 2/25/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/25/2020 DINAH GARIN
Sewer availability Cleared 2/25/2020 DINAH GARIN
Green Code Cleared 3/31/2020 RICHARD GARCIA
ZA Case Cleared 4/3/2020 MAXFIELD VERMY
ZA Case Cleared 4/3/2020 MAXFIELD VERMY
Construction near power lines Cleared 4/8/2020 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 5/4/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2020 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 9/23/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 9/23/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Conditional Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 10/22/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 10/22/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 10/22/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 10/22/2020 Corrections Issued JOHNNY MIRANDA
Sewer 10/27/2020 Approved OGANES TARAKHCHYAN
Special/Order Compliance 10/27/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/29/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/29/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 10/29/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/29/2020 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 11/5/2020 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 11/5/2020 Corrections Issued KENNETH NAGLE
Green Building Rough 11/5/2020 Approved KENNETH NAGLE
HVAC-Rough 11/5/2020 Approved KENNETH NAGLE
Interior/Exterior Lathing 11/5/2020 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 11/13/2020 Approved RICHARD ROBLES
ELECTRICAL-Rough 11/13/2020 Approved RICHARD ROBLES
Insulation 11/23/2020 Approved ANDREW NAVE
Drywall Nailing 12/1/2020 Approved RICHARD ROBLES
ELECTRICAL-Final 12/4/2020 Not Ready for Inspection RICHARD ROBLES
Gas Test 12/4/2020 Approved RICHARD ROBLES
Shower Pan 12/4/2020 Approved RICHARD ROBLES
Underground Mechanical 12/4/2020 Approved RICHARD ROBLES
ELECTRICAL-Final 3/16/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Final 3/16/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 3/16/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 3/16/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 3/16/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/16/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 3/16/2021 Approved OGANES TARAKHCHYAN
Pre-Inspection 3/22/2021 Corrections Issued EVAN COOPER
Final 4/5/2021 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/5/2021 SGSOV Not Ready EVAN COOPER
Final 4/13/2021 Conditional Approval KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved KENNETH NAGLE