6441 W 84TH ST 90045

Certificate Information: 6441 W 84TH ST 90045

Application / Permit
19014-30000-05767
Plan Check / Job No.
B19WL05946
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Single story addition and renovation to (E) kitchen and addition of (n) family room and male bath to an (e) SFD. (n) floor area is 486 sqft.
Permit Issued
Issued on 2/11/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 MANUEL GARCIA
Corrections Issued 10/25/2019 MANUEL GARCIA
Building Plans Picked Up 11/12/2019 APPLICANT
Plan Check Approved 12/11/2019 ALFREDO JARA
Issued 2/11/2020 LADBS
CofO in Progress 9/7/2021 ENRIQUE MIRELES
CofO in Progress 9/7/2021 ENRIQUE MIRELES
CofO Issued 9/21/2021 RONALD MYRICK
Permit Finaled 9/21/2021 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/11/2019 DINAH GARIN
Roof/Waste drainage to street Cleared 12/11/2019 DINAH GARIN
Sewer availability Cleared 12/11/2019 DINAH GARIN

Contact Information

Contractor Zweifel G L Construction; Lic. No.: 424637-B 1512 PACIFIC ST      SANTA MONICA, CA 90405

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 7/30/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 7/30/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 7/30/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/25/2020 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 9/22/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 9/30/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 9/30/2020 Approved JOHNNY MIRANDA
Green Building Rough 9/30/2020 Approved JOHNNY MIRANDA
HVAC-Rough 9/30/2020 Approved JOHNNY MIRANDA
Insulation 10/6/2020 Approved JOHNNY MIRANDA
Drywall Nailing 10/16/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/16/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 7/9/2021 Not Ready for Inspection JUAN VALENZUELA
Final 7/9/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 7/9/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 7/9/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 7/9/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Final 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 9/7/2021 Approved ENRIQUE MIRELES
Final 9/7/2021 OK to Issue CofO ENRIQUE MIRELES
Footing/Foundation/Slab 9/7/2021 Approved ENRIQUE MIRELES