6441 W 84TH ST 90045
Certificate Information: 6441 W 84TH ST 90045
- Application / Permit
- 19014-30000-05767
- Plan Check / Job No.
- B19WL05946
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Single story addition and renovation to (E) kitchen and addition of (n) family room and male bath to an (e) SFD. (n) floor area is 486 sqft.
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | MANUEL GARCIA |
| Corrections Issued | 10/25/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Plan Check Approved | 12/11/2019 | ALFREDO JARA |
| Issued | 2/11/2020 | LADBS |
| CofO in Progress | 9/7/2021 | ENRIQUE MIRELES |
| CofO in Progress | 9/7/2021 | ENRIQUE MIRELES |
| CofO Issued | 9/21/2021 | RONALD MYRICK |
| Permit Finaled | 9/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/11/2019 | DINAH GARIN |
| Sewer availability | Cleared | 12/11/2019 | DINAH GARIN |
Contact Information
| Contractor | Zweifel G L Construction; Lic. No.: 424637-B | 1512 PACIFIC ST SANTA MONICA, CA 90405 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/30/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/30/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/22/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/30/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/30/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/30/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 9/30/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 10/6/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 10/16/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/16/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/9/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 7/9/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/9/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 7/9/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 7/9/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 9/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | ENRIQUE MIRELES |
| Final | 9/7/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/7/2021 | Approved | ENRIQUE MIRELES |