3651 W BOYCE AVE 90039

Certificate Information: 3651 W BOYCE AVE 90039

Application / Permit
19014-30000-05659
Plan Check / Job No.
B19WL05822
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION OF 356 SF INCREASING THE SZ OF 3RD BEDROOM W/ A (N0 MASTER BATH & A WALK IN CLOSET, REMODELING (E) KITCHEN & CREATING A (N) PANTRY, (N) POWDER ROOM, & (N) LAUNDRY ROOM
Permit Issued
Issued on 12/24/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 MANUEL GARCIA
Corrections Issued 10/25/2019 MANUEL GARCIA
Building Plans Picked Up 11/8/2019 APPLICANT
Plan Check Approved 11/22/2019 KAVIAN REFAHI
Issued 12/24/2019 LADBS
CofO in Progress 10/26/2020 HAMIK HARTOUNIAN
Permit Finaled 10/28/2020 DEROLD HAUFF
CofO Issued 10/28/2020 DEROLD HAUFF
Permit Finaled 10/28/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2019 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 11/22/2019 DENNIS BRAGIN
Sewer availability Cleared 11/22/2019 DENNIS BRAGIN
ZA Case Cleared 11/22/2019 NOAH MCCOY

Contact Information

Engineer Carrizosa,, Richard Garcia; Lic. No.: C86224 1505 LYNDHURST AVE      HACIENDA HEIGHTS, CA 917452932

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2020 Conditional Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 1/9/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/13/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 1/27/2020 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/29/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/10/2020 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/10/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 2/10/2020 Approved HAMIK HARTOUNIAN
Insulation 2/12/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/20/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/20/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 4/20/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/20/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 4/20/2020 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 4/24/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 4/29/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/29/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/29/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/5/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/28/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 5/28/2020 Corrections Issued HAMIK HARTOUNIAN
Insulation 6/2/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/9/2020 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 6/9/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 6/9/2020 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 6/19/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/26/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/26/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/26/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 6/26/2020 Approved HAMIK HARTOUNIAN
Insulation 6/26/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/2/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/2/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/5/2020 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 8/5/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/11/2020 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 9/18/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/18/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 10/9/2020 Approved HAMIK HARTOUNIAN
Final 10/9/2020 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/9/2020 Approved HAMIK HARTOUNIAN
Green Building Final 10/9/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 10/9/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Final 10/9/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/9/2020 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 10/9/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 10/20/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 10/20/2020 Approved HAMIK HARTOUNIAN
Service/Power Release 10/20/2020 Approved HAMIK HARTOUNIAN
Final 10/26/2020 OK to Issue CofO HAMIK HARTOUNIAN