2489 S WESTGATE AVE 90064
Certificate Information: 2489 S WESTGATE AVE 90064
- Application / Permit
- 19014-30000-05650
- Plan Check / Job No.
- B19WL05813
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND FLOOR ADDITION AND MAJOR REMODEL TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | SERGIO SILVA |
| Corrections Issued | 11/18/2019 | SERGIO SILVA |
| Quality Review Completed | 11/27/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Applicant returned to address corrections | 1/30/2020 | SERGIO SILVA |
| Plan Check Approved | 2/13/2020 | SERGIO SILVA |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 8/27/2021 | KENNETH NAGLE |
| Permit Finaled | 8/27/2021 | KENNETH NAGLE |
| CofO Issued | 8/27/2021 | KENNETH NAGLE |
| Permit Finaled | 8/27/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | THOMAS LANG |
| Permit | Cleared | 2/7/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/7/2020 | THOMAS LANG |
| Green Code | Cleared | 2/12/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 2/12/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/13/2020 | JOHN CONNEALLY |
Contact Information
| Contractor | G L Construction Group Inc; Lic. No.: 994049-B | 324 S DIAMOND BAR BLVD STE 367 DIAMOND BAR, CA 91765 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 900 N SANTA ANITA AVE STE B ARCADIA, CA 91006 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 5/4/2020 | Approved | TIM CHRISTENSEN |
| PLUMBING-Rough | 5/4/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 5/15/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/20/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 5/20/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| MERV13>=Rough | 5/20/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/20/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/27/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 6/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/23/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 9/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 9/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/23/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2020 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| MERV13>=Rough | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 10/23/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 10/23/2020 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/23/2020 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 10/28/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/28/2020 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 11/4/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/4/2020 | Partial Approval | OGANES TARAKHCHYAN |
| MERV13>=Rough | 11/4/2020 | Approved | OGANES TARAKHCHYAN |
| Insulation | 11/23/2020 | Approved | RICHARD ROBLES |
| Interior/Exterior Lathing | 11/23/2020 | Approved | RICHARD ROBLES |
| Drywall Nailing | 12/3/2020 | Approved | RICHARD ROBLES |
| Shower Pan | 2/4/2021 | Approved | RICHARD ROBLES |
| Final | 6/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 6/24/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Final | 6/24/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 6/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 7/20/2021 | Corrections Issued | KENNETH NAGLE |
| Special/Order Compliance | 8/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Final | 8/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 8/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/18/2021 | Conditional Approval | KENNETH NAGLE |
| Green Building Final | 8/18/2021 | Approved | KENNETH NAGLE |
| Smoke Detectors | 8/18/2021 | Approved | KENNETH NAGLE |