12837 W RUBENS AVE 90066

Certificate Information: 12837 W RUBENS AVE 90066

Application / Permit
19014-30000-05639
Plan Check / Job No.
B19WL05805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND FLOOR ADDITION AND MAJOR REMODEL TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING WITH NEW ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 12/12/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 SERGIO SILVA
Green Plans Picked Up 11/5/2019 APPLICANT
Corrections Issued 11/6/2019 SERGIO SILVA
Quality Review Completed 11/14/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/22/2019 APPLICANT
Applicant returned to address corrections 12/3/2019 SERGIO SILVA
Plan Check Approved 12/11/2019 SERGIO SILVA
Issued 12/12/2019 LADBS
CofO in Progress 10/22/2020 PIERRE VEGA
Permit Finaled 10/29/2020 VINCENT COTTON
CofO Issued 10/29/2020 VINCENT COTTON
Permit Finaled 10/29/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2019 DINAH GARIN
Permit Cleared 11/22/2019 DINAH GARIN
Sewer availability Cleared 11/22/2019 DINAH GARIN
Green Code Cleared 12/5/2019 DONALD CRICHLOW
Low Impact Development Cleared 12/9/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/9/2019 ANTHONY MAINEZ
Trees in Parkway Cleared 12/9/2019 JOHN KIM
Hydrant and Access approval Cleared 12/11/2019 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/22/2020 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/23/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/23/2020 Partial Approval JUAN VALENZUELA
METHANE-Barrier 1/23/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 1/23/2020 Approved JUAN VALENZUELA
Underground Mechanical 1/23/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/3/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/4/2020 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/2/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 4/2/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 4/8/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/29/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 5/21/2020 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 5/22/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 5/22/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 5/26/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 5/26/2020 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 6/3/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/3/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 6/4/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 6/4/2020 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 6/4/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 6/9/2020 Approved JOHNNY MIRANDA
Green Building Rough 6/9/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/9/2020 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 6/10/2020 Approved JOHNNY MIRANDA
Insulation 6/11/2020 Approved JOHNNY MIRANDA
Drywall Nailing 6/16/2020 Approved JOHNNY MIRANDA
Gas Test 9/1/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/14/2020 Approved JOHNNY MIRANDA
Final 9/14/2020 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/14/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/14/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/14/2020 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 9/14/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/16/2020 Approved JOHNNY MIRANDA
Final 9/16/2020 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/16/2020 Approved JOHNNY MIRANDA
HVAC-Final 9/16/2020 Approved JOHNNY MIRANDA
PLUMBING-Final 9/16/2020 Approved JOHNNY MIRANDA
Final 10/19/2020 Partial Approval JOHNNY MIRANDA
Service/Power Release 10/19/2020 Approved JOHNNY MIRANDA