11602 W FRANCIS PL 90066
Certificate Information: 11602 W FRANCIS PL 90066
- Application / Permit
- 19014-30000-05598
- Plan Check / Job No.
- B19WL05750
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION TO AN (E) 1-STORY SFD WITH (N) ATTACHED GARAGE
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/30/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/8/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Plan Check Approved | 2/4/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 11/9/2020 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/23/2021 | KENNETH NAGLE |
| CofO Issued | 12/23/2021 | KENNETH NAGLE |
| Permit Finaled | 12/23/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/17/2019 | AMMAR ELTAWIL |
| Permit | Cleared | 12/17/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/17/2019 | ERIK BEASLEY |
| Green Code | Cleared | 12/19/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | DINAH GARIN |
| Trees in Parkway | Cleared | 1/30/2020 | JOHN KIM |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/2/2020 | Conditional Approval | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 3/6/2020 | Approved | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 3/6/2020 | Approved | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Wood Construction | 4/24/2020 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/4/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/6/2020 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/11/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 5/19/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 5/26/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/8/2020 | Conditional Approval | DAVID FEILER |
| Green Building Rough | 6/8/2020 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/8/2020 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 6/8/2020 | Conditional Approval | DAVID FEILER |
| Insulation | 6/10/2020 | Approved | EVAN COOPER |
| Shower Pan | 6/10/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/12/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 6/18/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/22/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Drywall Nailing | 6/25/2020 | Approved | EVAN COOPER |
| Underground Mechanical | 8/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/27/2020 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 8/27/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/27/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/27/2020 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 9/8/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/8/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/9/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/17/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/24/2020 | Approved | EVAN COOPER |
| Final | 9/24/2020 | Corrections Issued | EVAN COOPER |
| Green Building Final | 9/24/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 9/24/2020 | Approved | EVAN COOPER |
| Final | 10/5/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 10/5/2020 | Approved | JOHNNY MIRANDA |
| Final | 10/30/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 11/6/2020 | OK to Issue CofO | OGANES TARAKHCHYAN |