2206 S VETERAN AVE 90064

Certificate Information: 2206 S VETERAN AVE 90064

Application / Permit
19014-30000-05597
Plan Check / Job No.
B19WL05745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Existing single story SFD addition on 1st floor and new 2nd floor. New attached garage.
Permit Issued
Issued on 1/17/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 MANUEL GARCIA
Corrections Issued 12/3/2019 MANUEL GARCIA
Green Plans Picked Up 12/9/2019 APPLICANT
Quality Review Completed 12/11/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/17/2019 APPLICANT
Plan Check Approved 1/16/2020 MANUEL GARCIA
Issued 1/17/2020 LADBS
CofO in Progress 1/14/2021 KENNETH NAGLE
Permit Finaled 1/19/2021 KENNETH NAGLE
CofO Issued 1/19/2021 KENNETH NAGLE
Permit Finaled 1/19/2021 KENNETH NAGLE

Permit Application Clearance Information

Permit Cleared 12/23/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/30/2019 ANTHONY MAINEZ
Sewer availability Cleared 12/30/2019 ANTHONY MAINEZ
Low Impact Development Cleared 1/13/2020 JORGE MEJIA LEMUS
Green Code Cleared 1/15/2020 RICHARD GARCIA
Roof/Waste drainage to street Cleared 1/15/2020 ANTHONY MAINEZ
GPI Written Notices Cleared 1/16/2020 MANUEL GARCIA
Grading Pre-Inspection Cleared 1/16/2020 MANUEL GARCIA
Grading Pre-Inspection Cleared 1/16/2020 MANUEL GARCIA

Contact Information

Contractor K Y S S Construction; Lic. No.: 965244-B 616 N JACKSON ST #103      GLENDALE, CA 91206

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2020 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 3/6/2020 Approved KEVIN BEAULIEU
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Conditional Approval TIM CHRISTENSEN
Green Building Rough 6/8/2020 Not Ready for Inspection TIM CHRISTENSEN
ELECTRICAL-Rough 6/12/2020 Corrections Issued KENNETH NAGLE
HVAC-Rough 6/12/2020 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 6/12/2020 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 6/16/2020 Not Ready for Inspection JUSTIN CURTIS
Gas Test 6/16/2020 Not Ready for Inspection JUSTIN CURTIS
HVAC-Rough 6/16/2020 Not Ready for Inspection JUSTIN CURTIS
PLUMBING-Rough 6/16/2020 Not Ready for Inspection JUSTIN CURTIS
ELECTRICAL-Rough 6/17/2020 Partial Approval JUSTIN CURTIS
HVAC-Rough 6/17/2020 Approved JUSTIN CURTIS
PLUMBING-Rough 6/19/2020 Approved JUSTIN CURTIS
Gas Test 6/25/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/25/2020 Corrections Issued OGANES TARAKHCHYAN
Shower Pan 6/29/2020 Approved JUSTIN CURTIS
Insulation 7/6/2020 Corrections Issued JUSTIN CURTIS
Insulation 7/7/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/23/2020 Approved JUSTIN CURTIS
Grounding or Bonding 9/8/2020 Conditional Approval EVAN COOPER
Service/Power Release 9/8/2020 Approved EVAN COOPER
Gas Test 9/29/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/6/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 10/6/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 10/26/2020 Corrections Issued EVAN COOPER
HVAC-Final 10/26/2020 Approved EVAN COOPER
PLUMBING-Final 10/26/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Final 11/12/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Final 11/12/2020 Approved KENNETH NAGLE
PLUMBING-Final 11/12/2020 Corrections Issued KENNETH NAGLE
ELECTRICAL-Final 11/18/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 11/18/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/2/2020 Not Ready for Inspection RICHARD ROBLES
Final 12/2/2020 Not Ready for Inspection RICHARD ROBLES
Green Building Final 12/2/2020 Not Ready for Inspection RICHARD ROBLES
Green Building Rough 12/2/2020 Not Ready for Inspection RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 12/2/2020 SGSOV Not Ready RICHARD ROBLES
Smoke Detectors 12/2/2020 Not Ready for Inspection RICHARD ROBLES
BUILDING-Rough-Frame 12/22/2020 Approved RICHARD ROBLES
Final 12/22/2020 Conditional Approval RICHARD ROBLES
Green Building Final 12/22/2020 Approved RICHARD ROBLES
Green Building Rough 12/22/2020 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 12/22/2020 SGSOV Approved RICHARD ROBLES
Smoke Detectors 12/22/2020 Approved RICHARD ROBLES