1633 S GENESEE AVE 90019

Certificate Information: 1633 S GENESEE AVE 90019

Application / Permit
19014-30000-05577
Plan Check / Job No.
B19WL05720
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel & 1-story addition to (e) 1-story single family dwelling
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 11/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 REZA HAGHIGHAT
Corrections Issued 11/12/2019 REZA HAGHIGHAT
Quality Review Completed 11/18/2019 FELIX FIGUEROA
Green Plans Picked Up 12/4/2019 APPLICANT
Applicant returned to address corrections 4/20/2020 REZA HAGHIGHAT
Plan Check Approved 4/20/2020 REZA HAGHIGHAT
Building Plans Picked Up 1/20/2021 APPLICANT
Issued 3/16/2021 APPLICANT
CofO in Progress 11/21/2025 ARTHUR NEGRETE
Permit Finaled 11/23/2025 DEROLD HAUFF
CofO Issued 11/23/2025 DEROLD HAUFF
Permit Finaled 11/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 2/24/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/24/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/26/2020 ANTHONY MAINEZ
Green Code Cleared 3/12/2020 RICHARD GARCIA
Sewer availability Cleared 3/12/2020 ANTHONY MAINEZ

Contact Information

Architect Devarajan,, Anand; Lic. No.: C30243 12641 MARCO PLACE      LOS ANGELES, CA 90066
Contractor Bedrock Build And Design Inc; Lic. No.: 961595-B P O BOX 1086      SIMI VALLEY, CA 93062
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 12831 PANAMA STREET      LOS ANGELES, CA 90066

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2021 Not Ready for Inspection RUBEN SALAS
METHANE-Barrier 5/27/2021 Corrections Issued RUBEN SALAS
METHANE-Subgrade 5/27/2021 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 6/4/2021 Partial Approval STUART CHAPMAN
METHANE-Rough 6/4/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/6/2021 Approved STUART CHAPMAN
METHANE-Barrier 7/6/2021 Approved STUART CHAPMAN
METHANE-Subgrade 7/6/2021 Approved STUART CHAPMAN
PLUMBING-Rough 7/6/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Conditional Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/6/2021 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 10/6/2021 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 11/19/2021 Partial Approval JOSE AVILA
ELECTRICAL-Rough 11/19/2021 Corrections Issued JOSE AVILA
Green Building Rough 11/19/2021 Partial Approval JOSE AVILA
HVAC-Rough 11/19/2021 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/19/2021 Approved JOSE AVILA
Rough-Elec/Plmb/HVAC 11/19/2021 Corrections Issued JOSE AVILA
Insulation 12/17/2021 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 12/17/2021 Approved JOSE AVILA
Drywall Nailing 12/28/2021 Approved JOSE AVILA
Green Building Rough 12/28/2021 Approved JOSE AVILA
Insulation 12/28/2021 Approved JOSE AVILA
Interior/Exterior Lathing 1/4/2022 Approved JOSE AVILA
Shower Pan 1/18/2022 Approved JOSE AVILA
Sewer 4/5/2022 Approved JOSE AVILA
HVAC-Final 5/31/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/12/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/12/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 12/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 12/12/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 12/12/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 12/12/2022 Approved ALIZAH MAYAGOITIA
Final 5/16/2023 Corrections Issued JOSE AVILA
Green Building Final 5/16/2023 Approved JOSE AVILA
Special/Order Compliance 11/3/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Final 2/11/2025 Corrections Issued ARTHUR NEGRETE
HVAC-Final 2/11/2025 Approved ARTHUR NEGRETE
Final 10/16/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 11/19/2025 Approved ARTHUR NEGRETE
Final 11/19/2025 OK to Issue CofO ARTHUR NEGRETE