10330 W BANNOCKBURN DR 90064

Certificate Information: 10330 W BANNOCKBURN DR 90064

Application / Permit
19014-30000-05455
Plan Check / Job No.
B19WL05616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of existing detached garage to an accessory dwelling unit (ADU) at the rear of the lot per ordinance.
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Assigned to Plan Check Engineer 10/9/2019 REZA HAGHIGHAT
Corrections Issued 10/10/2019 REZA HAGHIGHAT
Applicant returned to address corrections 6/2/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/16/2020 PARISA ZAHABI
Applicant returned to address corrections 7/30/2020 ALFREDO JARA
Applicant returned to address corrections 8/12/2020 PARISA ZAHABI
Applicant returned to address corrections 8/20/2020 RICHARD GARCIA
Plan Check Approved 8/31/2020 MANUEL GARCIA
Issued 10/16/2020 APPLICANT
Building Plans Picked Up 10/16/2020 APPLICANT
CofO in Progress 5/17/2023 CLAYTON GRAHAM
Permit Finaled 5/20/2023 DANIEL ORRANTE
CofO Issued 5/20/2023 DANIEL ORRANTE
Permit Finaled 5/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/1/2019 BRIAN OLSON
Address approval Cleared 11/5/2019 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/5/2019 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 11/5/2019 ANTHONY MAINEZ
Sewer availability Cleared 11/5/2019 ANTHONY MAINEZ
Construction near power lines Cleared 2/26/2020 ERNEST FRESQUEZ
Hydrant and Access approval Cleared 5/22/2020 GEORGE SUCHAND

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/30/2020 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/8/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/5/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 3/5/2021 Not Ready for Inspection KEVIN SARGSYAN
Pre-Inspection 3/5/2021 Partial Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 4/5/2021 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval KEVIN SARGSYAN
Green Building Rough 4/5/2021 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 4/5/2021 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 8/26/2021 Corrections Issued KEVIN SARGSYAN
Green Building Rough 8/26/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 1/26/2022 Corrections Issued BRENDAN LOONEY
Sewer 1/26/2022 Corrections Issued BRENDAN LOONEY
Sewer 2/2/2022 Approved KRISTEN CAUSEY
PLUMBING-Rough 2/10/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 3/17/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 3/17/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 3/17/2022 Approved KEVIN SARGSYAN
HVAC-Rough 3/17/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 3/17/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 3/17/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 4/28/2022 Approved KEVIN SARGSYAN
HVAC-Rough 4/28/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/28/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/9/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/14/2023 Approved CLAYTON GRAHAM
Final 4/14/2023 Corrections Issued CLAYTON GRAHAM
Green Building Final 4/14/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 4/14/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 4/14/2023 Corrections Issued CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Not Ready CLAYTON GRAHAM
Smoke Detectors 4/14/2023 Not Ready for Inspection CLAYTON GRAHAM
Drywall Nailing 5/4/2023 Approved CLAYTON GRAHAM
Final 5/4/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 5/4/2023 Approved CLAYTON GRAHAM
Gas Test 5/4/2023 Approved CLAYTON GRAHAM
Green Building Final 5/4/2023 Approved CLAYTON GRAHAM
HVAC-Final 5/4/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 5/4/2023 Approved CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/4/2023 SGSOV Approved CLAYTON GRAHAM
Service/Power Release 5/4/2023 Not Ready for Inspection CLAYTON GRAHAM
Smoke Detectors 5/4/2023 Approved CLAYTON GRAHAM
Final 5/12/2023 OK to Issue CofO CLAYTON GRAHAM
Service/Power Release 5/15/2023 Approved CLAYTON GRAHAM