6639 N TYRONE AVE 91405

Certificate Information: 6639 N TYRONE AVE 91405

Application / Permit
19014-30000-05435
Plan Check / Job No.
B19WL05597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of garage to ADU per AB494 & SB229.
Permit Issued
Issued on 2/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 10/23/2019 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 10/25/2019 APPLICANT
Quality Review Completed 11/1/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/4/2019 APPLICANT
Plan Check Approved 1/23/2020 VLADIMIR ARUTYUNYAN
Issued 2/3/2020 LADBS
CofO in Progress 7/22/2021 MICHEL ABAJAN
Permit Finaled 1/15/2022 MICHAEL SMITH
CofO Issued 1/15/2022 MICHAEL SMITH
Permit Finaled 1/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 12/10/2019 ORVAL HERNANDEZ-MARCI
Address approval Cleared 12/13/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/13/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 12/13/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/13/2019 EMIL KYUPELYAN
HPOZ Cleared 12/27/2019 SUKI GERSHENHORN
Green Code Cleared 1/21/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2020 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/19/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/19/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 4/10/2020 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 7/1/2020 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 7/1/2020 Not Ready for Inspection BEAU COLLINS
Green Building Rough 7/1/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 7/2/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval MISAEL ESPARZA
Sewer 7/7/2020 Approved MISAEL ESPARZA
Underground Mechanical 7/7/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 7/15/2020 Corrections Issued DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Partial Approval DANIEL DREW
HVAC-Rough 7/15/2020 Approved DANIEL DREW
PLUMBING-Rough 7/15/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 7/22/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 7/22/2020 Not Ready for Inspection WILLIAM KUEHN
Insulation 7/22/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 7/22/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Inspection WILLIAM KUEHN
Wood Frame 7/28/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 8/20/2020 Approved BEAU COLLINS
Green Building Rough 8/20/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 8/20/2020 Partial Approval BEAU COLLINS
Insulation 8/24/2020 Approved WILLIAM KUEHN
Drywall Nailing 8/31/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/9/2020 Approved WILLIAM KUEHN
Final 3/15/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 3/15/2021 Approved MICHAEL TEMPLE
Green Building Final 3/15/2021 Not Ready for Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready MICHAEL TEMPLE
Service/Power Release 3/15/2021 Not Ready for Inspection MICHAEL TEMPLE
Smoke Detectors 3/15/2021 Approved MICHAEL TEMPLE
Final 5/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 5/5/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Approved ARTHUR SARGSYAN
Final 6/1/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 7/22/2021 Approved MICHEL ABAJAN
Final 7/22/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 7/22/2021 Approved MICHEL ABAJAN
HVAC-Final 7/22/2021 Approved MICHEL ABAJAN
PLUMBING-Final 7/22/2021 Approved MICHEL ABAJAN
Service/Power Release 7/22/2021 Approved MICHEL ABAJAN