6637 N TYRONE AVE 91405
Certificate Information: 6637 N TYRONE AVE 91405
- Application / Permit
- 19014-30000-05434
- Plan Check / Job No.
- B19WL05597
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel and addition to (e) SFD. Comply with department order effective date 11.06.2019. Permit will expire 30 days from issuance date.
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/23/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 10/25/2019 | APPLICANT |
| Quality Review Completed | 11/1/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Plan Check Approved | 1/23/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 2/3/2020 | LADBS |
| CofO in Progress | 6/11/2021 | BRYAN MEYER |
| CofO in Progress | 6/11/2021 | BRYAN MEYER |
| CofO Issued | 6/15/2021 | DAVID JAMES |
| Permit Finaled | 6/15/2021 | DAVID JAMES |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/10/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| HPOZ | Cleared | 12/27/2019 | SUKI GERSHENHORN |
| Green Code | Cleared | 1/21/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2020 | No Access for Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Approved | BRYAN MEYER |
| Wood Frame | 2/28/2020 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 6/11/2020 | Partial Inspection | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 6/11/2020 | Partial Inspection | BRYAN MEYER |
| BUILDING-Rough-Frame | 7/1/2020 | Partial Approval | BRYAN MEYER |
| ELECTRICAL-Rough | 7/1/2020 | Approved | BRYAN MEYER |
| Green Building Rough | 7/1/2020 | Partial Approval | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 7/1/2020 | Approved | BRYAN MEYER |
| Insulation | 8/24/2020 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 8/24/2020 | Partial Approval | BRYAN MEYER |
| Drywall Nailing | 8/31/2020 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 9/9/2020 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | BRYAN MEYER |
| Final | 3/15/2021 | Partial Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 3/15/2021 | Approved | BRYAN MEYER |
| Green Building Final | 3/15/2021 | Approved | BRYAN MEYER |
| Green Building Rough | 3/15/2021 | Approved | BRYAN MEYER |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Not Ready | BRYAN MEYER |
| Service/Power Release | 3/15/2021 | Not Ready for Inspection | BRYAN MEYER |
| Smoke Detectors | 3/15/2021 | Approved | BRYAN MEYER |
| Final | 4/26/2021 | Partial Approval | BRYAN MEYER |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Approved | BRYAN MEYER |
| Final | 5/5/2021 | Partial Approval | BRYAN MEYER |
| Final | 6/11/2021 | OK to Issue CofO | BRYAN MEYER |