16589 W VIA FLORESTA 90272

Certificate Information: 16589 W VIA FLORESTA 90272

Application / Permit
19014-30000-05422
Plan Check / Job No.
B19WL05585
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel, remove trellis, enclose (e) covered patio @ (e) 2-story SFD. Per engineering design.
Permit Issued
Issued on 1/17/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/9/2019 ALFREDO JARA
Corrections Issued 10/11/2019 ALFREDO JARA
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 1/16/2020 MANUEL GARCIA
Issued 1/17/2020 LADBS
CofO in Progress 5/18/2020 ANDREW NAVE
Permit Finaled 6/2/2020 VINCENT COTTON
CofO Issued 6/2/2020 VINCENT COTTON
Permit Finaled 6/2/2020 VINCENT COTTON

Permit Application Clearance Information

Coastal Zone Cleared 1/15/2020 DENZEL HENDERSON
Coastal Zone Cleared 1/15/2020 DENZEL HENDERSON
Coastal Zone Cleared 1/15/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 1/15/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 1/15/2020 DINAH GARIN
Grading Pre-Inspection Cleared 1/16/2020 KIRK LINKLATER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Simril Design And Construction; Lic. No.: 473668-B 2A KONTIKI WAY      PACIFIC PALISADES, CA 90272

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 2/13/2020 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 2/13/2020 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Approved ANDREW NAVE
Green Building Rough 2/13/2020 Approved ANDREW NAVE
HVAC-Rough 2/13/2020 Approved ANDREW NAVE
Insulation 2/13/2020 Approved ANDREW NAVE
Drywall Nailing 2/21/2020 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 2/21/2020 Partial Approval MICHAEL TEMPLE
PLUMBING-Final 4/24/2020 Corrections Issued ANDREW NAVE
HVAC-Final 4/27/2020 Approved ANDREW NAVE
PLUMBING-Final 4/27/2020 Approved ANDREW NAVE
ELECTRICAL-Final 4/30/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 5/4/2020 Approved ANDREW NAVE
ELECTRICAL-Final 5/4/2020 Approved ANDREW NAVE
Final 5/4/2020 Conditional Approval ANDREW NAVE
Green Building Final 5/4/2020 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 5/4/2020 SGSOV Approved ANDREW NAVE
Smoke Detectors 5/4/2020 Approved ANDREW NAVE