16054 W TEMECULA ST 90272
Certificate Information: 16054 W TEMECULA ST 90272
- Application / Permit
- 19014-30000-05278
- Plan Check / Job No.
- B19WL05460
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY RESIDENCE W/ ATT. 2-CAR GARAGE
- Permit Issued
- Issued on 5/4/2020
- Issuing Office
- Current Status
- CofO Issued on 11/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | REZA HAGHIGHAT |
| Corrections Issued | 10/7/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 10/17/2019 | APPLICANT |
| Quality Review Completed | 10/18/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/27/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 5/4/2020 | REZA HAGHIGHAT |
| Issued | 5/4/2020 | APPLICANT |
| Building Plans Picked Up | 5/6/2020 | APPLICANT |
| CofO in Progress | 11/12/2020 | ANDREW NAVE |
| CofO Issued | 11/18/2020 | VINCENT COTTON |
| Permit Finaled | 11/18/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/30/2019 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 1/27/2020 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/27/2020 | REZA HAGHIGHAT |
| Green Code | Cleared | 1/28/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 1/29/2020 | ORVAL HERNANDEZ-MARCI |
| Permit | Cleared | 1/29/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/29/2020 | JEANIE LAM |
| Trees in Parkway | Cleared | 1/29/2020 | ADRIAN SANCHEZ |
| Coastal Zone | Cleared | 5/4/2020 | LOUIS ORTEGA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/27/2020 | Approved | ANDREW NAVE |
| Underground Mechanical | 5/27/2020 | Approved | ANDREW NAVE |
| Sewer | 5/28/2020 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/4/2020 | Corrections Issued | ANDREW NAVE |
| Pre-Inspection | 6/4/2020 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 6/19/2020 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 7/17/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 7/21/2020 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2020 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 7/24/2020 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 7/24/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 7/28/2020 | Approved | ANDREW NAVE |
| Shower Pan | 7/28/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 7/29/2020 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 8/3/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 8/3/2020 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 8/3/2020 | Approved | ANDREW NAVE |
| Insulation | 8/7/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/17/2020 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 9/2/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 10/23/2020 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 10/23/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 10/23/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 10/27/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 10/30/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 10/30/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 10/30/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 11/5/2020 | Approved | ANDREW NAVE |
| Final | 11/5/2020 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 11/5/2020 | Approved | ANDREW NAVE |
| Green Building Final | 11/5/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 11/5/2020 | Not Ready for Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 11/5/2020 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 11/5/2020 | Approved | ANDREW NAVE |
| HVAC-Final | 11/6/2020 | Approved | ANDREW NAVE |
| Final | 11/12/2020 | OK to Issue CofO | ANDREW NAVE |
| Service/Power Release | 11/12/2020 | Approved | ANDREW NAVE |