612-614 E WESTMINSTER AVE 90291
Certificate Information: 612-614 E WESTMINSTER AVE 90291
- Application / Permit
- 19014-30000-04996
- Plan Check / Job No.
- B19WL05133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2-story addition to existing 2-story duplex
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- Issued on 8/26/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | SERGIO SILVA |
| Corrections Issued | 9/30/2019 | MARJAN SHENASI |
| Quality Review Completed | 10/10/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/19/2019 | MARJAN SHENASI |
| Applicant returned to address corrections | 3/3/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/7/2020 | MARJAN SHENASI |
| Green Plans Picked Up | 5/27/2020 | APPLICANT |
| Applicant returned to address corrections | 7/20/2020 | MARJAN SHENASI |
| Plan Check Approved | 8/26/2020 | MARJAN SHENASI |
| Issued | 8/26/2020 | APPLICANT |
| Building Plans Picked Up | 8/27/2020 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/18/2019 | ANNA VAN |
| Miscellaneous | Cleared | 12/18/2019 | ANNA VAN |
| Miscellaneous | Cleared | 12/18/2019 | ANNA VAN |
| Miscellaneous | Cleared | 12/18/2019 | ANNA VAN |
| Specific Plan | Cleared | 2/12/2020 | IRA BROWN |
| Coastal Zone | Cleared | 2/24/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 3/4/2020 | VALERIA CEJA |
| Specific Plan | Cleared | 3/4/2020 | VALERIA CEJA |
| Housing rent stabilization | Cleared | 3/9/2020 | ISMAEL HERNANDEZ |
| Green Code | Cleared | 5/27/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 8/10/2020 | TRACY TATE |
Contact Information
| Contractor | Consumer Unlimited; Lic. No.: 680701-B | 2804 NORTH GRAND AVENUE COVINA, CA 91724 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Not Ready for Inspection | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Conditional Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 9/30/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 9/30/2020 | Not Ready for Inspection | DAVID HEINE |
| METHANE-Rough | 9/30/2020 | Approved | DAVID HEINE |
| Wood Frame | 10/5/2020 | Partial Approval | DAVID HEINE |
| Wood Frame | 10/8/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 12/18/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 12/18/2020 | Corrections Issued | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 12/18/2020 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Rough | 12/18/2020 | Corrections Issued | DAVID HEINE |
| ELECTRICAL-Rough | 12/22/2020 | Corrections Issued | DAVID HEINE |
| ELECTRICAL-Rough | 12/24/2020 | Approved | DAVID HEINE |
| Insulation | 12/29/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 12/29/2020 | Partial Approval | DAVID HEINE |
| Drywall Nailing | 1/7/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/7/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 2/24/2021 | Approved | JOHNNY MIRANDA |
| Final | 2/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/24/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 2/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 2/24/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Barrier | 2/24/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 2/24/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 2/24/2021 | Approved | JOHNNY MIRANDA |
| Final | 3/31/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 3/31/2021 | Approved | JOHNNY MIRANDA |
| Final | 4/29/2021 | Corrections Issued | JOHNNY MIRANDA |