1529 S WELLESLEY AVE 90025
Certificate Information: 1529 S WELLESLEY AVE 90025
- Application / Permit
- 19014-30000-04893
- Plan Check / Job No.
- B19WL05060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2nd-floor addition to (e) 2-story SFD at rear of the lot.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2019 | REZA HAGHIGHAT |
| Corrections Issued | 9/23/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 9/30/2019 | APPLICANT |
| Quality Review Completed | 10/4/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/7/2019 | APPLICANT |
| Plan Check Approved | 12/30/2019 | REZA HAGHIGHAT |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 10/12/2023 | CARLOS MATAMOROS |
| No Progress | 10/16/2023 | MICHAEL PELHAM |
| CofO in Progress | 10/31/2023 | MICHAEL PELHAM |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
| CofO Issued | 10/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2019 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 10/18/2019 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 10/18/2019 | NIKTA MOUSAVI |
| Green Code | Cleared | 12/18/2019 | RICHARD GARCIA |
Contact Information
| Architect | Glynn,, Frank Christopher; Lic. No.: C19159 | 233 CALIFORNIA STREET EL SEGUNDO, CA 90245 |
| Contractor | Owner-Builder | , |
| Engineer | Hashemi,, Jafar; Lic. No.: C62010 | 26009 CALMHILL DR TORRANCE, CA 90505 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 6/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/20/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 11/20/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/22/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/24/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/1/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/25/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/4/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/8/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 4/20/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 4/21/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 4/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Final | 4/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 4/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 4/29/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/9/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/2/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/12/2022 | Approved | ASHLEY THOMPSON |
| Final | 10/12/2022 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 10/12/2022 | Approved | ASHLEY THOMPSON |
| Green Building Final | 10/12/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 10/12/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 10/12/2022 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 10/12/2022 | Approved | ASHLEY THOMPSON |
| Gas Test | 2/2/2023 | Approved | DAVID FEILER |
| PLUMBING-Final | 2/2/2023 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 2/8/2023 | Partial Inspection | CLAYTON GRAHAM |
| HVAC-Final | 2/8/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 2/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 2/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 2/24/2023 | Approved | CLAYTON GRAHAM |
| Final | 9/29/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 9/29/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 10/11/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 10/11/2023 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 10/16/2023 | Corrections Issued | MICHAEL PELHAM |