11534 W THURSTON CIR 90049
Certificate Information: 11534 W THURSTON CIR 90049
- Application / Permit
- 19014-30000-04803
- Plan Check / Job No.
- B19WL04968
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert (e) garage & addition as second story to ADU per AB494 and SB229
- Permit Issued
- Issued on 12/3/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/25/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2019 | KAVIAN REFAHI |
| Corrections Issued | 9/23/2019 | KAVIAN REFAHI |
| Quality Review Completed | 10/4/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/4/2019 | APPLICANT |
| Green Plans Picked Up | 10/4/2019 | APPLICANT |
| Applicant returned to address corrections | 10/29/2019 | KAVIAN REFAHI |
| Plan Check Approved | 11/15/2019 | KAVIAN REFAHI |
| Issued | 12/3/2019 | LADBS |
| CofO in Progress | 9/18/2020 | CARLOS MATAMOROS |
| Permit Finaled | 9/25/2020 | VINCENT COTTON |
| CofO Issued | 9/25/2020 | VINCENT COTTON |
| Permit Finaled | 9/25/2020 | VINCENT COTTON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/23/2019 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 9/23/2019 | KAVIAN REFAHI |
| Address approval | Cleared | 10/16/2019 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 10/16/2019 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 10/16/2019 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 10/16/2019 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | OSCAR GUTIERREZ |
| Green Code | Cleared | 11/6/2019 | RICHARD GARCIA |
| Sewer availability | Cleared | 11/6/2019 | OSCAR GUTIERREZ |
Contact Information
| Contractor | Hines Construction Inc; Lic. No.: 804870-B | 825 INDIANA AVENUE VENICE, CA 90291 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/17/2019 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Drilled-In Anchors | 1/6/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/8/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 2/13/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2020 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 2/19/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/19/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/27/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/27/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/27/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/10/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 3/10/2020 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 3/10/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/12/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 3/17/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/31/2020 | Approved | ANTHONY MCDOWALL |
| Underground Mechanical | 5/11/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 6/2/2020 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 6/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 6/12/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 6/12/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Gas Test | 6/16/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 6/16/2020 | Partial Approval | ANTHONY MCDOWALL |
| Gas Test | 6/23/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/21/2020 | Approved | CARLOS MATAMOROS |
| Final | 8/21/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/21/2020 | Approved | CARLOS MATAMOROS |
| Green Building Final | 8/21/2020 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 8/21/2020 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/21/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/31/2020 | Approved | CARLOS MATAMOROS |
| Final | 8/31/2020 | Partial Approval | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/31/2020 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 9/4/2020 | Partial Approval | CARLOS MATAMOROS |
| Final | 9/9/2020 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Final | 9/9/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/9/2020 | Approved | CARLOS MATAMOROS |