3158 W SILVERADO DR 90039

Certificate Information: 3158 W SILVERADO DR 90039

Application / Permit
19014-30000-04800
Plan Check / Job No.
B19WL04966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Kitchen remodel and addition to (E) SFD.
Permit Issued
Issued on 10/29/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2019 APPLICANT
Assigned to Plan Check Engineer 9/4/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 9/6/2019 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 9/18/2019 APPLICANT
Plan Check Approved 10/8/2019 MANUEL GARCIA
Issued 10/29/2019 LADBS
CofO in Progress 9/21/2020 ARTHUR SARGSYAN
Permit Finaled 9/29/2020 DEROLD HAUFF
CofO Issued 9/29/2020 DEROLD HAUFF
Permit Finaled 9/29/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/3/2019 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 10/3/2019 MAHELET GEBEYHU
Grading Pre-Inspection Cleared 10/8/2019 KIRK LINKLATER

Contact Information

Contractor S K Construction; Lic. No.: 633705-B 901 CALLE SERRA      SAN DIMAS, CA 91773
Engineer Chang,, Wayne Chia-Wei; Lic. No.: S4751 19210 S VERMONT AVE BLDG B STE 210      GARDENA, CA 90248

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/5/2020 No Access for Inspection BRAD BESCOS
PLUMBING-Rough 2/13/2020 Partial Approval JOSEPH MCGARRY
Sewer 2/13/2020 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 3/31/2020 Approved JOSEPH MCGARRY
Deputy Wood Construction 3/31/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 5/12/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 5/12/2020 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 5/15/2020 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 5/15/2020 Approved JOSEPH MCGARRY
HVAC-Rough 5/15/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/15/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/15/2020 Approved JOSEPH MCGARRY
Insulation 5/29/2020 Partial Inspection THOMAS LOGRASSO
Insulation 6/3/2020 Approved JOSEPH MCGARRY
Drywall Nailing 6/8/2020 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Not Ready JOSEPH MCGARRY
BUILDING-Rough-Frame 9/18/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 9/18/2020 Approved ARTHUR SARGSYAN
Final 9/18/2020 OK to Issue CofO ARTHUR SARGSYAN
Footing/Foundation/Slab 9/18/2020 Approved ARTHUR SARGSYAN
Green Building Final 9/18/2020 Approved ARTHUR SARGSYAN
Green Building Rough 9/18/2020 Approved ARTHUR SARGSYAN
PLUMBING-Final 9/18/2020 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/18/2020 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 9/18/2020 Approved ARTHUR SARGSYAN