3158 W SILVERADO DR 90039
Certificate Information: 3158 W SILVERADO DR 90039
- Application / Permit
- 19014-30000-04800
- Plan Check / Job No.
- B19WL04966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Kitchen remodel and addition to (E) SFD.
- Permit Issued
- Issued on 10/29/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/6/2019 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 9/18/2019 | APPLICANT |
| Plan Check Approved | 10/8/2019 | MANUEL GARCIA |
| Issued | 10/29/2019 | LADBS |
| CofO in Progress | 9/21/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 9/29/2020 | DEROLD HAUFF |
| CofO Issued | 9/29/2020 | DEROLD HAUFF |
| Permit Finaled | 9/29/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2019 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 10/3/2019 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 10/8/2019 | KIRK LINKLATER |
Contact Information
| Contractor | S K Construction; Lic. No.: 633705-B | 901 CALLE SERRA SAN DIMAS, CA 91773 |
| Engineer | Chang,, Wayne Chia-Wei; Lic. No.: S4751 | 19210 S VERMONT AVE BLDG B STE 210 GARDENA, CA 90248 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/5/2020 | No Access for Inspection | BRAD BESCOS |
| PLUMBING-Rough | 2/13/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 2/13/2020 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 3/31/2020 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 3/31/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/12/2020 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/12/2020 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/15/2020 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/15/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/15/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 5/29/2020 | Partial Inspection | THOMAS LOGRASSO |
| Insulation | 6/3/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/8/2020 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Not Ready | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| Final | 9/18/2020 | OK to Issue CofO | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 9/18/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 9/18/2020 | Approved | ARTHUR SARGSYAN |