972 E VERNON AVE 90291
Certificate Information: 972 E VERNON AVE 90291
- Application / Permit
- 19014-30000-04544
- Plan Check / Job No.
- B19WL04724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to an exisitng 1-story s.f.d. w/ a new attached garage and roof truss
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Green Plans Picked Up | 9/13/2009 | APPLICANT |
| Submitted | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 9/10/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 9/19/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Applicant returned to address corrections | 12/5/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/27/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 3/5/2021 | JOHNNY MIRANDA |
| CofO Issued | 3/16/2021 | VINCENT COTTON |
| Permit Finaled | 3/16/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 10/29/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/29/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/29/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 11/6/2019 | DONALD CRICHLOW |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/2/2020 | Partial Approval | DAVID HEINE |
| Sewer | 4/2/2020 | Approved | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 4/28/2020 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 4/28/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | No Access for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Conditional Approval | DAVID HEINE |
| Deputy Wood Construction | 7/30/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Approval | DAVID HEINE |
| Gas Test | 8/5/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 8/5/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 8/17/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 8/17/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 8/17/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 8/19/2020 | Approved | DAVID HEINE |
| Green Building Rough | 8/19/2020 | Approved | DAVID HEINE |
| Shower Pan | 8/19/2020 | Approved | DAVID HEINE |
| Insulation | 8/24/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 9/1/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 9/1/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Final | 11/10/2020 | Approved | DAVID HEINE |
| Gas Test | 11/10/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 11/10/2020 | Approved | DAVID HEINE |
| Service/Power Release | 11/10/2020 | Not Ready for Inspection | DAVID HEINE |
| Special/Order Compliance | 11/10/2020 | Partial Inspection | PIERRE VEGA |
| HVAC-Final | 11/12/2020 | No Access for Inspection | DAVID HEINE |
| Smoke Detectors | 11/12/2020 | No Access for Inspection | DAVID HEINE |
| Final | 1/27/2021 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 1/27/2021 | Approved | DAVID HEINE |
| Green Building Final | 1/27/2021 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Approved | DAVID HEINE |
| Smoke Detectors | 1/27/2021 | Approved | DAVID HEINE |
| HVAC-Final | 2/26/2021 | Approved | JOHNNY MIRANDA |
| Final | 3/5/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Service/Power Release | 3/8/2021 | Approved | JOHNNY MIRANDA |