972 E VERNON AVE 90291

Certificate Information: 972 E VERNON AVE 90291

Application / Permit
19014-30000-04544
Plan Check / Job No.
B19WL04724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition to an exisitng 1-story s.f.d. w/ a new attached garage and roof truss
Permit Issued
Issued on 1/27/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Green Plans Picked Up 9/13/2009 APPLICANT
Submitted 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/10/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 9/19/2019 FELIX FIGUEROA
Building Plans Picked Up 9/26/2019 APPLICANT
Applicant returned to address corrections 12/5/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/27/2020 KAMRAN GHOTBI RAVANDI
Issued 1/27/2020 LADBS
CofO in Progress 3/5/2021 JOHNNY MIRANDA
CofO Issued 3/16/2021 VINCENT COTTON
Permit Finaled 3/16/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 GUILLERMO PETRA
Low Impact Development Cleared 10/29/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/29/2019 GUILLERMO PETRA
Sewer availability Cleared 10/29/2019 GUILLERMO PETRA
Green Code Cleared 11/6/2019 DONALD CRICHLOW

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/2/2020 Partial Approval DAVID HEINE
Sewer 4/2/2020 Approved DAVID HEINE
Excavation/Setback/Form/Re-Bar 4/28/2020 Approved DAVID HEINE
Footing/Foundation/Slab 4/28/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 No Access for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Conditional Approval DAVID HEINE
Deputy Wood Construction 7/30/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Partial Approval DAVID HEINE
Gas Test 8/5/2020 Approved DAVID HEINE
PLUMBING-Rough 8/5/2020 Approved DAVID HEINE
ELECTRICAL-Rough 8/17/2020 Approved DAVID HEINE
HVAC-Rough 8/17/2020 Approved DAVID HEINE
Interior/Exterior Lathing 8/17/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 8/19/2020 Approved DAVID HEINE
Green Building Rough 8/19/2020 Approved DAVID HEINE
Shower Pan 8/19/2020 Approved DAVID HEINE
Insulation 8/24/2020 Approved DAVID HEINE
Drywall Nailing 9/1/2020 Approved DAVID HEINE
Interior/Exterior Lathing 9/1/2020 Partial Approval DAVID HEINE
ELECTRICAL-Final 11/10/2020 Approved DAVID HEINE
Gas Test 11/10/2020 Approved DAVID HEINE
PLUMBING-Final 11/10/2020 Approved DAVID HEINE
Service/Power Release 11/10/2020 Not Ready for Inspection DAVID HEINE
Special/Order Compliance 11/10/2020 Partial Inspection PIERRE VEGA
HVAC-Final 11/12/2020 No Access for Inspection DAVID HEINE
Smoke Detectors 11/12/2020 No Access for Inspection DAVID HEINE
Final 1/27/2021 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 1/27/2021 Approved DAVID HEINE
Green Building Final 1/27/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved DAVID HEINE
Smoke Detectors 1/27/2021 Approved DAVID HEINE
HVAC-Final 2/26/2021 Approved JOHNNY MIRANDA
Final 3/5/2021 OK to Issue CofO JOHNNY MIRANDA
Service/Power Release 3/8/2021 Approved JOHNNY MIRANDA