3440 S MEIER ST 90066

Certificate Information: 3440 S MEIER ST 90066

Application / Permit
19014-30000-04540
Plan Check / Job No.
B19WL04720
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition to existing 1-story s.f.r w/ attached garage with roof trusses
Permit Issued
Issued on 1/27/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/31/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/10/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 9/16/2019 APPLICANT
Quality Review Completed 9/19/2019 FELIX FIGUEROA
Building Plans Picked Up 9/26/2019 APPLICANT
Applicant returned to address corrections 12/5/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/27/2020 KAMRAN GHOTBI RAVANDI
Issued 1/27/2020 LADBS
CofO in Progress 3/16/2021 ENRIQUE MIRELES
Permit Finaled 3/31/2021 VINCENT COTTON
CofO Issued 3/31/2021 VINCENT COTTON
Permit Finaled 3/31/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 GUILLERMO PETRA
Low Impact Development Cleared 10/29/2019 ANDRES COVARRUBIAS
Permit Cleared 10/29/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 10/29/2019 GUILLERMO PETRA
Sewer availability Cleared 10/29/2019 GUILLERMO PETRA
Trees in Parkway Cleared 10/29/2019 JOHN KIM
Green Code Cleared 11/6/2019 DONALD CRICHLOW

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2020 Partial Approval DAVID FEILER
Sewer 4/22/2020 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 4/30/2020 Approved DAVID FEILER
Footing/Foundation/Slab 4/30/2020 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Approved ANTHONY MCDOWALL
Gas Test 7/16/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 7/16/2020 Corrections Issued ANTHONY MCDOWALL
Deputy Wood Construction 7/21/2020 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 7/30/2020 Approved KENNETH NAGLE
BUILDING-Rough-Frame 8/11/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/11/2020 Approved JOHNNY MIRANDA
Green Building Rough 8/11/2020 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/11/2020 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 8/11/2020 Approved JOHNNY MIRANDA
HVAC-Rough 8/17/2020 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 8/17/2020 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 8/24/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/24/2020 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/26/2020 Approved EVAN COOPER
Green Building Rough 8/26/2020 Approved EVAN COOPER
HVAC-Rough 8/26/2020 Approved EVAN COOPER
Insulation 8/26/2020 Approved EVAN COOPER
Interior/Exterior Lathing 8/26/2020 Partial Approval EVAN COOPER
Drywall Nailing 9/1/2020 Approved CRAIG DAVIS
Interior/Exterior Lathing 9/1/2020 Partial Approval CRAIG DAVIS
Interior/Exterior Lathing 9/3/2020 Approved DAVID HEINE
HVAC-Final 1/7/2021 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 1/21/2021 Approved ENRIQUE MIRELES
Gas Test 1/21/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 1/21/2021 Corrections Issued ENRIQUE MIRELES
HVAC-Final 2/1/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 2/1/2021 Approved ENRIQUE MIRELES
Final 3/10/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/10/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/10/2021 Approved ENRIQUE MIRELES
Smoke Detectors 3/10/2021 Approved ENRIQUE MIRELES
Service/Power Release 3/12/2021 Approved JOHNNY MIRANDA
Final 3/16/2021 OK to Issue CofO ENRIQUE MIRELES