6426 W 85TH PL 90045

Certificate Information: 6426 W 85TH PL 90045

Application / Permit
19014-30000-04506
Plan Check / Job No.
B19WL04682
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to (E) 1 story SFD.
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2019 APPLICANT
Assigned to Plan Check Engineer 8/21/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 8/21/2019 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 8/28/2019 APPLICANT
Plan Check Approved 10/11/2019 REZA HAGHIGHAT
Issued 3/16/2020 LADBS
CofO in Progress 4/26/2025 DAVID FEILER
Permit Finaled 4/26/2025 RICHARD STEINBACH
CofO Issued 4/26/2025 RICHARD STEINBACH
Permit Finaled 4/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/10/2019 THOMAS LANG
Sewer availability Cleared 10/10/2019 THOMAS LANG
Low Impact Development Cleared 10/11/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/11/2019 JEANETTE VONG

Contact Information

Architect Chun,, Youngmin; Lic. No.: C32890 1828 LINCOLN BLVD #B      SANTA MONICA, CA 90404
Contractor Lazobuild Inc; Lic. No.: 1001909-B 3592 ROSEMEAD BLVD #219      ROSEMEAD, CA 91770
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/15/2020 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 6/2/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/2/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/5/2020 Approved JOHNNY MIRANDA
Underground Mechanical 6/5/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 9/22/2020 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 9/25/2020 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 10/2/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 10/2/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 10/2/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Approved JUAN VALENZUELA
Green Building Rough 10/9/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/19/2020 Approved JOHNNY MIRANDA
Green Building Rough 10/19/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/19/2020 Partial Approval JOHNNY MIRANDA
Insulation 10/23/2020 Corrections Issued PIERRE VEGA
Insulation 11/2/2020 Approved JOHNNY MIRANDA
Drywall Nailing 11/6/2020 Approved JOHNNY MIRANDA
Shower Pan 1/6/2021 Corrections Issued JOHNNY MIRANDA
Shower Pan 1/7/2021 Corrections Issued JOHNNY MIRANDA
Shower Pan 1/11/2021 Approved DAVID HEINE
Final 2/12/2021 Corrections Issued DAVID HEINE
Green Building Final 2/12/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved DAVID HEINE
Smoke Detectors 2/12/2021 Approved DAVID HEINE
Final 4/26/2025 OK to Issue CofO DAVID FEILER