5966-5968 W 86TH PL 90045

Certificate Information: 5966-5968 W 86TH PL 90045

Application / Permit
19014-30000-04395
Plan Check / Job No.
B19WL04535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Second story addition and first floor addition and major remodel to existing duplex.
Permit Issued
Issued on 8/11/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Green Plans Picked Up 8/27/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 9/3/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 9/5/2019 FELIX FIGUEROA
Building Plans Picked Up 9/10/2019 APPLICANT
Applicant returned to address corrections 11/25/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/12/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/22/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/28/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/18/2020 KAMRAN GHOTBI RAVANDI
Issued 8/11/2020 APPLICANT
CofO in Progress 1/26/2022 BOBBY KEY
Permit Finaled 2/1/2022 DANIEL ORRANTE
CofO Issued 2/1/2022 DANIEL ORRANTE
Permit Finaled 2/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Housing rent stabilization Cleared 9/30/2019 STEVEN HOFSTAD
Eng Process Fee Ord 176,300 Cleared 10/8/2019 ANTHONY MAINEZ
Sewer availability Cleared 10/8/2019 ANTHONY MAINEZ
Low Impact Development Cleared 10/28/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/28/2019 EMIL KYUPELYAN
Green Code Cleared 11/5/2019 RICHARD GARCIA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Focus Builders Inc; Lic. No.: 990023-B 3375 LIVONIA AVE      LOS ANGELES, CA 90034

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2020 Corrections Issued PIERRE VEGA
Excavation/Setback/Form/Re-Bar 12/28/2020 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 12/30/2020 No Access for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 12/31/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 1/11/2021 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 1/11/2021 Approved PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Corrections Issued DAVID HEINE
PLUMBING-Rough 1/12/2021 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 1/15/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/16/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Corrections Issued DAVID HEINE
PLUMBING-Rough 3/2/2021 Approved DAVID HEINE
ELECTRICAL-Rough 4/6/2021 Approved BRENDAN LOONEY
HVAC-Rough 4/6/2021 Approved BRENDAN LOONEY
Wood Frame 4/6/2021 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 4/8/2021 Conditional Approval BRENDAN LOONEY
Wood Frame 4/14/2021 Approved BRENDAN LOONEY
Drywall Nailing 4/30/2021 Approved BRENDAN LOONEY
Green Building Rough 4/30/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 4/30/2021 No Access for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 5/7/2021 Partial Approval KENNETH NAGLE
Shower Pan 5/7/2021 Approved KENNETH NAGLE
Interior/Exterior Lathing 5/28/2021 Partial Approval BRENDAN LOONEY
Underground Mechanical 8/25/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Final 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Gas Test 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Not Ready BRENDAN LOONEY
Service/Power Release 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 9/1/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 10/29/2021 Corrections Issued DAVID FEILER
Gas Test 10/29/2021 Approved DAVID FEILER
HVAC-Final 10/29/2021 Corrections Issued DAVID FEILER
PLUMBING-Final 10/29/2021 Approved DAVID FEILER
ELECTRICAL-Final 11/4/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Approved DAVID FEILER
Service/Power Release 11/4/2021 Approved DAVID FEILER
Smoke Detectors 11/4/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 12/28/2021 Approved ENRIQUE MIRELES
Final 12/28/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 12/28/2021 Approved ENRIQUE MIRELES
Green Building Final 12/28/2021 Approved ENRIQUE MIRELES
HVAC-Final 12/28/2021 Approved ENRIQUE MIRELES
Final 1/14/2022 Corrections Issued BOBBY KEY
Final 1/26/2022 OK to Issue CofO BOBBY KEY