2408 S CLOY AVE 90291

Certificate Information: 2408 S CLOY AVE 90291

Application / Permit
19014-30000-04393
Plan Check / Job No.
B19WL04532
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY ADDITION AND REMODEL TO EXISTING 1-STORY SFD WITH ATTACHED 1-CAR GARAGE. NEW NFPA-13D FIRE SPINKLERS THROUGHOUT.
Permit Issued
Issued on 4/8/2020
Issuing Office
Current Status
CofO Issued on 2/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 EMMANUEL MARTINEZ
Corrections Issued 9/16/2019 EMMANUEL MARTINEZ
Quality Review Completed 9/20/2019 KESETE HAREGOT
Green Plans Picked Up 9/25/2019 APPLICANT
Building Plans Picked Up 9/26/2019 APPLICANT
Plan Check Approved 1/27/2020 EMMANUEL MARTINEZ
Issued 4/8/2020 APPLICANT
CofO in Progress 2/3/2022 DAVID FEILER
Permit Finaled 2/11/2022 DANIEL ORRANTE
CofO Issued 2/11/2022 DANIEL ORRANTE
Permit Finaled 2/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 DINAH GARIN
Hydrant and Access approval Cleared 10/29/2019 JEREMY CARTER
Sewer availability Cleared 10/29/2019 DINAH GARIN
Low Impact Development Cleared 11/25/2019 SARAH YOUSSEF
Coastal Zone Cleared 11/26/2019 NOAH MCCOY
Miscellaneous Cleared 11/26/2019 NOAH MCCOY
Miscellaneous Cleared 11/26/2019 NOAH MCCOY
Roof/Waste drainage to street Cleared 11/26/2019 ANTHONY MAINEZ
Specific Plan Cleared 11/26/2019 NOAH MCCOY
ZI Cleared 11/26/2019 NOAH MCCOY
Green Code Cleared 12/3/2019 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/18/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 6/2/2020 Partial Approval DAVID HEINE
METHANE-Barrier 6/2/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 6/2/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 6/2/2020 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 6/9/2020 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 6/15/2020 Approved DAVID HEINE
Footing/Foundation/Slab 6/15/2020 Partial Approval DAVID HEINE
METHANE-Barrier 6/15/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 6/15/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 6/19/2020 Approved DAVID HEINE
METHANE-Barrier 6/23/2020 Approved DAVID HEINE
Deputy Reinf. Concrete 7/2/2020 Partial Approval DAVID HEINE
Rough-Elec/Plmb/HVAC 7/6/2020 Partial Approval DAVID HEINE
Underground Mechanical 7/6/2020 Partial Approval DAVID HEINE
Wood Frame 7/6/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 7/8/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 7/9/2020 Approved DAVID HEINE
Rough-Elec/Plmb/HVAC 7/9/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 7/23/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 8/20/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 9/9/2020 Partial Approval DAVID HEINE
Green Building Rough 9/9/2020 Not Ready for Inspection DAVID HEINE
METHANE-Rough 9/9/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 9/24/2020 Approved DAVID HEINE
ELECTRICAL-Rough 11/5/2020 Approved DAVID HEINE
Rough-Elec/Plmb/HVAC 11/5/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 11/20/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 11/20/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 11/20/2020 Corrections Issued JUAN VALENZUELA
METHANE-Rough 11/20/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 11/24/2020 Approved DAVID HEINE
Green Building Rough 11/24/2020 Approved DAVID HEINE
HVAC-Rough 11/24/2020 Approved DAVID HEINE
METHANE-Rough 11/24/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/3/2020 Partial Approval DAVID HEINE
Insulation 12/9/2020 Approved DAVID HEINE
Drywall Nailing 1/5/2021 Approved DAVID HEINE
Interior/Exterior Lathing 1/5/2021 Approved DAVID HEINE
Shower Pan 1/5/2021 Approved DAVID HEINE
ELECTRICAL-Final 9/15/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 10/18/2021 Corrections Issued DAVID FEILER
Final 10/18/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 10/18/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 10/18/2021 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 10/18/2021 Approved DAVID FEILER
ELECTRICAL-Final 11/16/2021 Approved DEANDRE HOFFMAN
HVAC-Final 11/16/2021 Approved DEANDRE HOFFMAN
PLUMBING-Final 11/16/2021 Approved DEANDRE HOFFMAN
Service/Power Release 11/18/2021 Approved DAVID FEILER
Final 12/8/2021 Corrections Issued DAVID FEILER
Green Building Final 12/8/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved DAVID FEILER
Final 2/3/2022 OK to Issue CofO DAVID FEILER
Green Building Final 2/3/2022 Approved DAVID FEILER