2340 N NOTTINGHAM AVE 90027

Certificate Information: 2340 N NOTTINGHAM AVE 90027

Application / Permit
19014-30000-04358
Plan Check / Job No.
B19WL04517
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) SFD AND CONVERT (E) ATTACHED GARAGE INTO LIVING AREA. ADDITION AT SECOND FLOOR.
Permit Issued
Issued on 1/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 SERGIO GUTIERREZ
Green Plans Picked Up 9/12/2019 APPLICANT
Corrections Issued 9/24/2019 SERGIO GUTIERREZ
Quality Review Completed 10/8/2019 KESETE HAREGOT
Building Plans Picked Up 10/10/2019 APPLICANT
Plan Check Approved 1/3/2020 SERGIO GUTIERREZ
Issued 1/7/2020 LADBS
CofO in Progress 11/18/2020 JOSEPH MCGARRY
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 10/29/2019 JEANIE LAM
Sewer availability Cleared 10/29/2019 JEANIE LAM
BHO/Hillside ordinance Cleared 11/12/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 11/12/2019 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 11/12/2019 EMIL KYUPELYAN
Miscellaneous Cleared 11/12/2019 ARMEN MEHRABIAN
Green Code Cleared 11/26/2019 RICHARD GARCIA
Hydrant and Access approval Cleared 12/9/2019 JEREMY CARTER
Grading Pre-Inspection Cleared 1/3/2020 SERGIO GUTIERREZ

Contact Information

Architect Myer,, Jamie Beekman; Lic. No.: C31042 1730 3/4 WESTWOOD BLVD      LOS ANGELES, CA 90024
Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 1836 PARNELL AVE 202      LOS ANGELES, CA 90025

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 1/9/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 1/9/2020 Approved ARTHUR SARGSYAN
Pre-Inspection 1/9/2020 Partial Approval ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/23/2020 Corrections Issued BRAD BESCOS
ELECTRICAL-Rough 1/23/2020 Corrections Issued BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Approval BRAD BESCOS
Green Building Rough 1/23/2020 Approved BRAD BESCOS
HVAC-Rough 1/23/2020 Approved BRAD BESCOS
PLUMBING-Rough 1/23/2020 Approved BRAD BESCOS
Insulation 1/31/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/10/2020 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/10/2020 Partial Approval JOSEPH MCGARRY
Insulation 2/10/2020 Approved JOSEPH MCGARRY
Drywall Nailing 2/21/2020 Approved BRAD BESCOS
Interior/Exterior Lathing 3/25/2020 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 4/15/2020 Partial Approval THOMAS LOGRASSO
Sewer 8/24/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/19/2020 Approved JOSEPH MCGARRY
Final 10/19/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 10/19/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 10/19/2020 Approved JOSEPH MCGARRY
Final 10/26/2020 Not Ready for Inspection JOSEPH MCGARRY
Service/Power Release 10/26/2020 Approved JOSEPH MCGARRY
Final 11/2/2020 Not Ready for Inspection ARTHUR SARGSYAN
Final 11/18/2020 OK to Issue CofO JOSEPH MCGARRY