1242 W 38TH ST 90037

Certificate Information: 1242 W 38TH ST 90037

Application / Permit
19014-30000-04193
Plan Check / Job No.
B19WL04363
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Bedroom & patio addition to rear of existing s.f.d. All work per IB/P/BC 2017-004 and IB/P/BC 2014-006 wood frame prescriptive provision.
Permit Issued
Issued on 1/31/2020
Issuing Office
West Los Angeles
Current Status
Issued on 1/31/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Building Plans Picked Up 8/15/2016 APPLICANT
Submitted 8/2/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 REZA HAGHIGHAT
Corrections Issued 8/9/2019 REZA HAGHIGHAT
Plan Check Approved 1/31/2020 MANUEL GARCIA
Issued 1/31/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/4/2019 JENNY CEA
Sewer availability Cleared 9/4/2019 JENNY CEA
ZI Cleared 9/4/2019 TREVOR MARTIN
Low Impact Development Cleared 1/24/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 1/31/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2020 Conditional Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Partial Approval ROBERT MCDOWELL
Insulation 3/11/2020 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 3/11/2020 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 3/25/2020 Corrections Issued ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/25/2020 Approved ROBERT MCDOWELL
Drywall Nailing 4/2/2020 Approved STUART CHAPMAN
Green Building Rough 4/2/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/2/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/12/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/12/2020 Corrections Issued ROBERT MCDOWELL
Final 5/12/2020 Not Ready for Inspection ROBERT MCDOWELL
Footing/Foundation/Slab 5/12/2020 Approved ROBERT MCDOWELL
Green Building Final 5/12/2020 Approved ROBERT MCDOWELL
HVAC-Final 5/12/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 5/12/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/12/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 5/12/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/27/2020 Approved ROBERT MCDOWELL
Final 5/27/2020 Conditional Approval ROBERT MCDOWELL