12846 W WALSH AVE 90066
Certificate Information: 12846 W WALSH AVE 90066
- Application / Permit
- 19014-30000-04095
- Plan Check / Job No.
- B19WL04269
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) 1-STORY SFD AND (N) ROOF FRAMING ENTIRELY. FULLY SPRINLKERED.
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2019 | APPLICANT |
| Green Plans Picked Up | 8/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 8/20/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/6/2019 | QUAN NGHIEM |
| Plan Check Approved | 3/9/2021 | SAMUEL GONZALEZ |
| Issued | 3/10/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| TCO Issued (Expire Date: 03-14-2023) | 9/15/2022 | DANIEL ORRANTE |
| CofO in Progress | 11/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/10/2022 | DANIEL ORRANTE |
| CofO Issued | 11/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 3/2/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 3/2/2020 | CATHERINE ADROVER |
| Green Code | Cleared | 3/19/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 1/22/2021 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | L A Construction Company Inc; Lic. No.: 826984-B | 11294 HAYTER AVE CULVER CITY, CA 90230 |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/27/2021 | Corrections Issued | ANTHONY MCDOWALL |
| METHANE-Barrier | 4/27/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| METHANE-Subgrade | 4/27/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 4/27/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/30/2021 | Partial Approval | ANTHONY MCDOWALL |
| METHANE-Barrier | 4/30/2021 | Approved | ANTHONY MCDOWALL |
| METHANE-Subgrade | 4/30/2021 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Rough | 5/19/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 5/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 5/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/14/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sewer | 9/14/2021 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 9/21/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/12/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 10/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 10/12/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 11/8/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 11/8/2021 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 11/8/2021 | Approved | DAVID FEILER |
| Wood Frame | 11/8/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 12/1/2021 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 12/1/2021 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 1/4/2022 | Approved | JOHN KAYON |
| Green Building Rough | 1/4/2022 | Approved | JOHN KAYON |
| HVAC-Rough | 1/4/2022 | Approved | JOHN KAYON |
| PLUMBING-Rough | 1/4/2022 | Approved | JOHN KAYON |
| Interior/Exterior Lathing | 1/7/2022 | Approved | JOHN KAYON |
| Insulation | 1/12/2022 | Approved | JOHN KAYON |
| Drywall Nailing | 2/4/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/4/2022 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 5/11/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/25/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 7/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 7/20/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/20/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/29/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/3/2022 | Approved | HERBERT GIRON |
| Final | 9/2/2022 | OK to Issue CofO | HERBERT GIRON |
| Footing/Foundation/Slab | 9/2/2022 | Approved | HERBERT GIRON |
| Green Building Final | 9/2/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 9/2/2022 | Approved | HERBERT GIRON |