4817 N BREWSTER DR 91356
Certificate Information: 4817 N BREWSTER DR 91356
- Application / Permit
- 19014-30000-04074
- Plan Check / Job No.
- B19WL04256
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (e) single family with attached garage.Fully Sprinklered.
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 8/21/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 9/6/2019 | QUAN NGHIEM |
| Green Plans Picked Up | 7/28/2020 | APPLICANT |
| Plan Check Approved | 4/6/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 4/7/2021 | APPLICANT |
| Issued | 11/12/2021 | APPLICANT |
| CofO in Progress | 4/10/2026 | JOHN KIDWELL |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
| CofO Issued | 4/11/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/18/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/18/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2019 | DINAH GARIN |
| Green Code | Cleared | 11/13/2019 | DONALD CRICHLOW |
| Grading Pre-Inspection | Cleared | 11/22/2019 | SAMUEL GONZALEZ |
| Low Impact Development | Cleared | 1/6/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/8/2020 | GABRIEL ROBLES |
| Private sewage disp. approval | Cleared | 3/17/2021 | DAN RYAN EVANGELISTA |
Contact Information
| Architect | Heeb,, Derek M; Lic. No.: C32338 | 406 BROADWAY 222C SANTA MONICA, CA 90401 |
| Contractor | Milestone Design & Development Inc; Lic. No.: 982639-B | 15233 VENTURA BLVD #425 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Partial Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Partial Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 3/11/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/18/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 3/18/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/24/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/24/2022 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 3/24/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Corrections Issued | DAVID SANDOVAL |
| Deputy Wood Construction | 5/3/2022 | Conditional Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 6/15/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 6/15/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 7/15/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 7/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 7/15/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | PETER FOLLING |
| Interior/Exterior Lathing | 8/29/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 7/29/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 7/29/2024 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Final | 7/29/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 10/23/2025 | Approved | JOHN KIDWELL |
| Final | 10/23/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 10/23/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 10/23/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 10/23/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 10/23/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 1/27/2026 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 1/27/2026 | Corrections Issued | JOHN KIDWELL |
| Final | 4/10/2026 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 4/10/2026 | Approved | JOHN KIDWELL |