4357 S PURDUE AVE 90066

Certificate Information: 4357 S PURDUE AVE 90066

Application / Permit
19014-30000-04043
Plan Check / Job No.
B19WL04227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTIOIN AND ADDITION TO EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, AND ADDITION OF NEW ATTACHED RECREATION ROOM.
Permit Issued
Issued on 3/31/2020
Issuing Office
West Los Angeles
Current Status
Issued on 3/31/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Assigned to Plan Check Engineer 7/31/2019 MANUEL GARCIA
Corrections Issued 8/5/2019 MANUEL GARCIA
Plan Check Approved 10/17/2019 SERGIO SILVA
Issued 3/31/2020 LADBS
Building Plans Picked Up 4/7/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/20/2019 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/20/2019 OSCAR GUTIERREZ
Sewer availability Cleared 8/20/2019 OSCAR GUTIERREZ
Construction near power lines Cleared 9/21/2019 RIDWAN HARDY
Low Impact Development Cleared 10/15/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/15/2019 OSCAR GUTIERREZ

Contact Information

Architect Poloukhine,, Michael; Lic. No.: C32850 3489 MAPLEWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/20/2020 Partial Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 6/25/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/25/2020 Not Ready for Inspection JOHNNY MIRANDA
Underground Mechanical 6/25/2020 Approved JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 7/2/2020 Approved CRAIG DAVIS
Footing/Foundation/Slab 7/2/2020 Approved CRAIG DAVIS
Gas Test 7/2/2020 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 7/20/2020 Not Ready for Inspection JUAN VALENZUELA
Sewer 8/5/2020 Approved ANTHONY MCDOWALL
Underground Mechanical 8/5/2020 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 6/16/2021 Corrections Issued ENRIQUE MIRELES
Service/Power Release 6/29/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/16/2021 Approved ENRIQUE MIRELES
HVAC-Rough 12/16/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/16/2021 Approved ENRIQUE MIRELES
Insulation 1/14/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/14/2022 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 3/21/2022 Approved STEPHANIE SWANSON
Green Building Rough 3/21/2022 Approved STEPHANIE SWANSON
Insulation 3/21/2022 Approved STEPHANIE SWANSON
Drywall Nailing 4/6/2022 Approved RYAN SALAZAR