1041 S STANLEY AVE 90019

Certificate Information: 1041 S STANLEY AVE 90019

Application / Permit
19014-30000-03863
Plan Check / Job No.
B19WL04050
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST AND 2ND FLOOR ADDITION AND CONVERT PORTION OF EXISTING GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 SERGIO SILVA
Building Plans Picked Up 8/23/2019 APPLICANT
Corrections Issued 8/26/2019 SERGIO SILVA
Quality Review Completed 9/5/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/8/2021 SERGIO SILVA
Applicant returned to address corrections 6/28/2021 SERGIO SILVA
Plan Check Approved 8/12/2021 SERGIO SILVA
Issued 10/6/2021 APPLICANT
CofO in Progress 8/7/2023 SCOTT FINNILA
Permit Finaled 8/8/2023 DEROLD HAUFF
CofO Issued 8/8/2023 DEROLD HAUFF
Permit Finaled 8/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/28/2020 RIDWAN HARDY
Construction within easement Cleared 1/28/2020 RIDWAN HARDY
CPC Cleared 7/31/2020 DANIEL MATA
CPC Cleared 7/31/2020 DANIEL MATA
HPOZ Cleared 7/31/2020 DANIEL MATA
ZI Cleared 7/31/2020 DANIEL MATA
Address approval Cleared 8/7/2020 ELAINE LEI
Permit Cleared 8/7/2020 ELAINE LEI
Sewer availability Cleared 8/7/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/11/2020 ELAINE LEI
Trees in Parkway Cleared 8/25/2020 JOHN KIM
Hydrant and Access approval Cleared 8/27/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/1/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 12/4/2020 ELAINE LEI
Green Code Cleared 3/8/2021 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2021 Partial Inspection ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 11/5/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 12/3/2021 Partial Approval DANIEL GONZALEZ
Underground Mechanical 12/21/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 1/10/2022 Approved ARTHUR SARGSYAN
METHANE-Barrier 1/10/2022 Approved ARTHUR SARGSYAN
METHANE-Final 1/10/2022 Approved ARTHUR SARGSYAN
METHANE-Subgrade 1/10/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 6/6/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 6/6/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 6/6/2022 Not Ready for Inspection ADAM ESCOTO
Wood Frame 6/6/2022 Corrections Issued ADAM ESCOTO
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection ADAM ESCOTO
ELECTRICAL-Rough 7/11/2022 Partial Approval ADAM ESCOTO
Green Building Rough 7/11/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 7/11/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 7/11/2022 Corrections Issued ADAM ESCOTO
Wood Frame 7/11/2022 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 7/19/2022 Approved ADAM ESCOTO
ELECTRICAL-Rough 7/19/2022 Approved ADAM ESCOTO
Green Building Rough 7/19/2022 Approved ADAM ESCOTO
HVAC-Rough 7/19/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/19/2022 Partial Approval ADAM ESCOTO
PLUMBING-Rough 7/19/2022 Approved ADAM ESCOTO
Wood Frame 7/19/2022 Approved ADAM ESCOTO
Insulation 7/29/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/10/2022 Partial Approval JEFFREY MEAD
Drywall Nailing 8/15/2022 Approved MICHAEL LEWIS
Underground Mechanical 8/29/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/20/2022 Approved MICHAEL LEWIS
Underground Mechanical 10/7/2022 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/9/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 5/9/2023 Approved RICHARD DOCKUS
PLUMBING-Final 5/9/2023 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Gas Company RICHARD DOCKUS
Smoke Detectors 5/9/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Final 5/12/2023 Approved RICHARD DOCKUS
HVAC-Final 5/12/2023 Approved RICHARD DOCKUS
PLUMBING-Final 5/12/2023 Approved RICHARD DOCKUS
Final 7/27/2023 Corrections Issued SCOTT FINNILA
Smoke Detectors 7/27/2023 Approved SCOTT FINNILA
Final 8/4/2023 OK to Issue CofO SCOTT FINNILA