4255 1/2 S LYCEUM AVE 90066

Certificate Information: 4255 1/2 S LYCEUM AVE 90066

Application / Permit
19014-30000-03800
Plan Check / Job No.
B19WL03977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd story addition to existing garage for ADU per AB494 and SB229 and ground floor addition to existing garage.
Permit Issued
Issued on 2/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 SAMUEL GONZALEZ
Corrections Issued 8/19/2019 SAMUEL GONZALEZ
Quality Review Completed 8/30/2019 QUAN NGHIEM
Green Plans Picked Up 9/3/2019 APPLICANT
Building Plans Picked Up 9/5/2019 APPLICANT
Plan Check Approved 11/7/2019 SAMUEL GONZALEZ
Issued 2/18/2020 LADBS
CofO in Progress 9/15/2022 DANIEL ORRANTE
Permit Finaled 9/15/2022 DANIEL ORRANTE
CofO Issued 9/15/2022 DANIEL ORRANTE
Permit Finaled 9/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/10/2019 ROBERT DUFF
Construction near power lines Cleared 10/25/2019 OSCAR CASTRO
Address approval Cleared 10/29/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/29/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 10/29/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 11/5/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 11/5/2019 JOHN LIN
Green Code Cleared 11/6/2019 RICHARD GARCIA

Contact Information

No Data Available.

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2020 Approved JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 5/4/2020 Approved DAVID FEILER
Wood Frame 5/28/2020 Partial Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 6/24/2020 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 6/24/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 6/26/2020 Approved DAVID HEINE
HVAC-Rough 6/26/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 6/26/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 7/7/2020 Partial Inspection DAVID HEINE
Green Building Rough 7/7/2020 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 8/5/2020 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 8/5/2020 Corrections Issued JOHNNY MIRANDA
Insulation 8/10/2020 Approved DAVID HEINE
Interior/Exterior Lathing 8/10/2020 Partial Approval DAVID HEINE
Drywall Nailing 8/24/2020 Approved DAVID HEINE
Green Building Rough 8/24/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/1/2020 Approved ENRIQUE MIRELES
Sewer 2/11/2021 Not Ready for Inspection ENRIQUE MIRELES
Gas Test 3/30/2021 Approved ENRIQUE MIRELES
Sewer 3/30/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/19/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 4/19/2022 Corrections Issued PATRICK QUALEY
Final 4/19/2022 Corrections Issued PATRICK QUALEY
Green Building Final 4/19/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 4/19/2022 Approved PATRICK QUALEY
Final 6/15/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved PATRICK QUALEY
Final 9/15/2022 Conditional Approval DANIEL ORRANTE