4255 S LYCEUM AVE 90066

Certificate Information: 4255 S LYCEUM AVE 90066

Application / Permit
19014-30000-03799
Plan Check / Job No.
B19WL03977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story remodel & addition to (e) 1-story sfd.
Permit Issued
Issued on 2/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 SAMUEL GONZALEZ
Corrections Issued 8/19/2019 SAMUEL GONZALEZ
Quality Review Completed 8/30/2019 QUAN NGHIEM
Green Plans Picked Up 9/3/2019 APPLICANT
Building Plans Picked Up 9/5/2019 APPLICANT
Plan Check Approved 11/7/2019 SAMUEL GONZALEZ
Issued 2/18/2020 LADBS
CofO in Progress 9/15/2022 DANIEL ORRANTE
Permit Finaled 9/15/2022 DANIEL ORRANTE
CofO Issued 9/15/2022 DANIEL ORRANTE
Permit Finaled 9/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 10/29/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 11/5/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 11/5/2019 JOHN LIN
Green Code Cleared 11/6/2019 RICHARD GARCIA

Contact Information

Contractor Ca Green Design Remodeling; Lic. No.: 1025818-B 6700 FALLBROOK AVE #192-A      WEST HILLS, CA 91307

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/3/2020 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 4/13/2020 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 4/16/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/16/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 5/4/2020 Partial Approval DAVID FEILER
Deputy Drilled-In Anchors 5/4/2020 Approved DAVID FEILER
Green Building Rough 5/4/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/4/2020 Partial Approval DAVID FEILER
Deputy Wood Construction 5/6/2020 Conditional Approval DAVID FEILER
Wood Frame 5/7/2020 Partial Approval DAVID FEILER
ELECTRICAL-Rough 6/24/2020 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Partial Approval JUAN VALENZUELA
HVAC-Rough 6/24/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 6/24/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 6/26/2020 Approved DAVID HEINE
HVAC-Rough 6/26/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 6/26/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 7/7/2020 Partial Approval DAVID HEINE
Green Building Rough 7/7/2020 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 8/4/2020 Partial Approval JOHNNY MIRANDA
Wood Frame 8/4/2020 Approved JOHNNY MIRANDA
Insulation 8/10/2020 Approved DAVID HEINE
Drywall Nailing 8/24/2020 Approved DAVID HEINE
Green Building Rough 8/24/2020 Approved DAVID HEINE
Shower Pan 11/24/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/1/2020 Approved ENRIQUE MIRELES
Sewer 3/30/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/4/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 4/27/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 4/27/2022 Corrections Issued PATRICK QUALEY
Final 4/27/2022 Not Ready for Inspection PATRICK QUALEY
Green Building Final 4/27/2022 Corrections Issued PATRICK QUALEY
HVAC-Final 4/27/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 4/27/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 4/27/2022 Approved PATRICK QUALEY
Final 6/15/2022 Corrections Issued PATRICK QUALEY
Green Building Final 6/15/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved PATRICK QUALEY
Final 9/15/2022 OK to Issue CofO DANIEL ORRANTE