2247 N MICHELTORENA ST 90039

Certificate Information: 2247 N MICHELTORENA ST 90039

Application / Permit
19014-30000-03734
Plan Check / Job No.
B19WL03911
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 of 3 Remodel & addition to (e) SFD w/detached garage.
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 ZAW HAN
Corrections Issued 8/5/2019 ZAW HAN
Green Plans Picked Up 8/7/2019 APPLICANT
Quality Review Completed 8/16/2019 HERNAN ARREOLA
Building Plans Picked Up 8/19/2019 APPLICANT
Applicant returned to address corrections 10/8/2019 ZAW HAN
Plan Check Approved 1/16/2020 ZAW HAN
Issued 1/16/2020 LADBS
CofO in Progress 12/27/2021 JOHN TCHANG
Permit Finaled 1/11/2022 DANIEL SANCHEZ
CofO Issued 1/11/2022 DANIEL SANCHEZ
Permit Finaled 1/11/2022 DANIEL SANCHEZ

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/19/2019 CELINA MORENO
BHO/Hillside ordinance Cleared 8/19/2019 CELINA MORENO
BHO/Hillside ordinance Cleared 8/19/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/19/2019 CELINA MORENO
Permit Cleared 8/19/2019 CELINA MORENO
Sewer availability Cleared 8/19/2019 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 9/27/2019 SARAH GOLDMAN
Green Code Cleared 10/3/2019 DONALD CRICHLOW
Low Impact Development Cleared 10/3/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/8/2019 ERIK BEASLEY
Trees in Parkway Cleared 11/30/2019 JOHN KIM
Disturb/Remove Protected Trees Cleared 12/20/2019 STEPHEN DUPREY
Grading Pre-Inspection Cleared 1/16/2020 ROBERT GOLD

Contact Information

Contractor Cinergy Construction Corp; Lic. No.: 1008486-B 2412 FEDERAL AVE_UNIT #1      LOS ANGELES, CA 90064
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384
Engineer Tsao,, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 2/5/2020 Partial Approval JOHN TCHANG
Masonry Wall/Backfill 2/19/2020 Approved JOHN TCHANG
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 3/5/2020 Partial Approval JOHN TCHANG
Masonry Wall/Backfill 3/5/2020 Partial Approval JOHN TCHANG
Excavation/Setback/Form/Re-Bar 4/1/2020 Partial Inspection GORDON ZUBER
Footing/Foundation/Slab 4/1/2020 Partial Inspection GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Corrections Issued GORDON ZUBER
Masonry Wall/Backfill 5/4/2020 Not Ready for Inspection JOHN TCHANG
Sewer 5/4/2020 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 5/11/2020 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 5/15/2020 Approved GORDON ZUBER
Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Inspection GORDON ZUBER
HVAC-Rough 9/10/2020 Partial Approval JOHN TCHANG
PLUMBING-Rough 9/18/2020 Approved EDDY ARDESSI
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Approved JOHN TCHANG
ELECTRICAL-Rough 9/24/2020 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 9/28/2020 Corrections Issued JOHN TCHANG
Green Building Rough 9/28/2020 Not Ready for Inspection JOHN TCHANG
BUILDING-Rough-Frame 9/30/2020 Corrections Issued JOHN TCHANG
ELECTRICAL-Rough 9/30/2020 Corrections Issued JOHN TCHANG
Green Building Rough 9/30/2020 Approved JOHN TCHANG
Insulation 10/5/2020 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 10/8/2020 Corrections Issued JOHN TCHANG
Insulation 10/8/2020 Partial Approval JOHN TCHANG
Interior/Exterior Lathing 10/29/2020 Approved JOHN TCHANG
Drywall Nailing 11/4/2020 Partial Approval JOHN TCHANG
Gas Test 3/2/2021 Not Ready for Inspection JOHN TCHANG
Underground Mechanical 3/2/2021 Approved JOHN TCHANG
Gas Test 3/4/2021 Approved JOHN TCHANG
Footing/Foundation/Slab 4/5/2021 Approved JOHN TCHANG
Masonry Wall/Backfill 4/19/2021 Approved JOHN TCHANG
Underground Mechanical 4/29/2021 Approved JOHN TCHANG
Gas Test 7/1/2021 Approved JOHN TCHANG
HVAC-Final 7/1/2021 Approved JOHN TCHANG
PLUMBING-Final 7/1/2021 Approved JOHN TCHANG
Sewer 8/30/2021 Approved JOHN TCHANG
Underground Mechanical 9/16/2021 Conditional Approval JOHN TCHANG
SUSMP-Std. Urban Storm Water 9/28/2021 Approved JOHN TCHANG
BUILDING-Rough-Frame 12/14/2021 Approved JOHN TCHANG
Drywall Nailing 12/14/2021 Approved JOHN TCHANG
Final 12/14/2021 Conditional Approval JOHN TCHANG
Green Building Final 12/14/2021 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Approved JOHN TCHANG
Smoke Detectors 12/14/2021 Approved JOHN TCHANG