7968 S MCCONNELL AVE 90045
Certificate Information: 7968 S MCCONNELL AVE 90045
- Application / Permit
- 19014-30000-03623
- Plan Check / Job No.
- B19WL03801
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 20'-4" X 17'-10" ATTACHED PATIO COVER TO (E) DWELLING
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2019 | MANUEL GARCIA |
| Corrections Issued | 7/5/2019 | MANUEL GARCIA |
| Plan Check Approved | 1/17/2020 | JEROME MAGAT PALMA |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 10/16/2023 | BOBBY KEY |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
| CofO Issued | 1/2/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 11/14/2019 | BARTON HOLMES |
| Low Impact Development | Cleared | 12/19/2019 | RYAN HUDSON |
| GPI Written Notices | Cleared | 1/17/2020 | JEROME MAGAT PALMA |
| Roof/Waste drainage to street | Cleared | 1/17/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 2/9/2021 | Not Ready for Inspection | DAVID HEINE |
| Drywall Nailing | 2/24/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 2/24/2021 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | BOBBY KEY |
| Final | 9/29/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/29/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 9/29/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 10/16/2023 | Approved | BOBBY KEY |
| Final | 10/16/2023 | OK to Issue CofO | BOBBY KEY |
| Smoke Detectors | 10/16/2023 | Approved | BOBBY KEY |