4810 S INGLEWOOD BLVD 90230

Certificate Information: 4810 S INGLEWOOD BLVD 90230

Application / Permit
19014-30000-03606
Plan Check / Job No.
B19WL03789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of existing SFD to attach to rear existing garage.
Permit Issued
Issued on 12/10/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2019 APPLICANT
Green Plans Picked Up 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 8/6/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/16/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 11/15/2019 VLADIMIR ARUTYUNYAN
Plan Check Approved 12/10/2019 VLADIMIR ARUTYUNYAN
Issued 12/10/2019 LADBS
Building Plans Picked Up 4/17/2020 APPLICANT
CofO in Progress 2/29/2024 JESUS RODRIGUEZ
Permit Finaled 3/6/2024 DANIEL ORRANTE
CofO Issued 3/6/2024 DANIEL ORRANTE
Permit Finaled 3/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 10/17/2019 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 10/21/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 10/21/2019 ELENA LOPEZ
Sewer availability Cleared 10/21/2019 ELENA LOPEZ
Green Code Cleared 11/7/2019 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ha,, Seungil; Lic. No.: S4164 3454 W 1ST ST      LOS ANGELES, CA 90004

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/21/2020 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/29/2020 Conditional Approval DAVID HEINE
Footing/Foundation/Slab 1/29/2020 Conditional Approval DAVID HEINE
BUILDING-Rough-Frame 3/2/2020 Partial Approval KENNETH NAGLE
Green Building Rough 3/2/2020 Not Ready for Inspection KENNETH NAGLE
Wood Frame 3/2/2020 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 5/15/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Not Ready for Inspection DAVID FEILER
Green Building Rough 5/15/2020 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 5/15/2020 Corrections Issued DAVID FEILER
Wood Frame 5/15/2020 Not Ready for Inspection DAVID FEILER
Special/Order Compliance 5/22/2020 No Access for Inspection CRAIG DAVIS
Footing/Foundation/Slab 9/28/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/3/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 1/3/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 2/14/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/11/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/1/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/10/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/10/2023 Approved JESUS RODRIGUEZ
Insulation 5/10/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/1/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 6/1/2023 Approved JESUS RODRIGUEZ
Final 11/21/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/21/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 11/21/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 1/9/2024 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 1/9/2024 Approved JESUS RODRIGUEZ
HVAC-Final 1/9/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 1/9/2024 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 1/9/2024 Corrections Issued JESUS RODRIGUEZ
Final 1/17/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 1/17/2024 Approved JESUS RODRIGUEZ
HVAC-Final 1/17/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 1/17/2024 Approved JESUS RODRIGUEZ
Final 1/30/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 1/30/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/30/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Not Ready JESUS RODRIGUEZ
Final 2/28/2024 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 3/4/2024 Approved JESUS RODRIGUEZ