12401 W DEERBROOK LANE 90049
Certificate Information: 12401 W DEERBROOK LANE 90049
- Application / Permit
- 19014-30000-03581
- Plan Check / Job No.
- B19WL03759
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Enclose irregular shape portion of patio cover to create recroom with bathroom. (111 sf) (6'-4" x 19'-5" & 15'-6")
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | MANUEL GARCIA |
| Corrections Issued | 7/17/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 7/18/2019 | APPLICANT |
| Plan Check Approved | 12/31/2019 | REZA HAGHIGHAT |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 5/17/2025 | MICHAEL PELHAM |
| Permit Finaled | 5/17/2025 | RICHARD STEINBACH |
| CofO Issued | 5/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/18/2019 | JENNY CEA |
| Sewer availability | Cleared | 7/18/2019 | JENNY CEA |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2019 | HISASHI KOBAYAKAWA |
| Hist. Property Cntrct Mgr Appr | Cleared | 11/27/2019 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 11/27/2019 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 11/27/2019 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 12/5/2019 | GEORGE SUCHAND |
| Grading Pre-Inspection | Cleared | 12/31/2019 | MANUEL GARCIA |
Contact Information
| Contractor | Romano Builders Inc; Lic. No.: 922936-B | 6308 WOODMAN AVE VALLEY GLEN, CA 91401 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2020 | Corrections Issued | TIM CHRISTENSEN |
| Underground Mechanical | 3/20/2020 | Partial Approval | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 6/11/2020 | Corrections Issued | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 6/11/2020 | Corrections Issued | TIM CHRISTENSEN |
| Green Building Rough | 6/11/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 8/11/2020 | Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | TIM CHRISTENSEN |
| Wood Frame | 8/14/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 8/21/2020 | Approved | ROBERT SHELLY |
| BUILDING-Rough-Frame | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 12/2/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/2/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 5/17/2025 | OK to Issue CofO | MICHAEL PELHAM |