1230 N LA COLLINA DR 90069
Certificate Information: 1230 N LA COLLINA DR 90069
- Application / Permit
- 19014-30000-03562
- Plan Check / Job No.
- B19WL03730
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel & addition to (e) s.f.d.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/30/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 8/15/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 8/16/2019 | APPLICANT |
| Applicant returned to address corrections | 9/30/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/11/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/21/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/10/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/17/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/30/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 12/8/2023 | RAUL BARAJAS |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2019 | EMIL KYUPELYAN |
| ZA Case | Cleared | 9/11/2019 | ANNA VAN |
| Miscellaneous | Cleared | 9/25/2019 | MARC WOERSCHING |
| Miscellaneous | Cleared | 9/25/2019 | MARC WOERSCHING |
| Hydrant and Access approval | Cleared | 10/16/2019 | JOHN CONNEALLY |
| BHO/Hillside ordinance | Cleared | 10/18/2019 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 10/18/2019 | THOMAS LANG |
| Permit | Cleared | 10/18/2019 | THOMAS LANG |
| Trees in Parkway | Cleared | 10/19/2019 | JOHN KIM |
| Low Impact Development | Cleared | 12/3/2019 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 12/10/2019 | RICHARD GARCIA |
| Excavation more than 5-ft deep | Cleared | 12/17/2019 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| Roof/Waste drainage to street | Cleared | 12/18/2019 | ELAINE LEI |
| Private sewage disp. approval | Cleared | 12/20/2019 | PATRICK MISCHLICH |
| BHO/Hillside ordinance | Cleared | 12/30/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/30/2019 | ANTHONY MAINEZ |
Contact Information
| Architect | Peck,, Christopher M; Lic. No.: C27316 | C.M. PECK CONSULTING 25 S. EL MOLINO AVE PASADENA, CA 911012023 |
| Contractor | Boswell Construction Inc; Lic. No.: 934480-B | 17071 VENTURA BLVD STE 201 ENCINO, CA 91316 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/21/2020 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/26/2020 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/29/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/1/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/2/2020 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/30/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 7/31/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 11/17/2020 | Conditional Approval | RAUL BARAJAS |
| Pre-Inspection | 7/26/2021 | Partial Inspection | RICHARD STEINBACH |
| PLUMBING-Rough | 10/4/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 10/20/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/22/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/17/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 11/17/2021 | Partial Approval | HORACE FULTZ |
| Deputy Reinf. Concrete | 11/18/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/19/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 12/2/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/10/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/21/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 2/17/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 2/23/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/7/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 3/18/2022 | Conditional Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 5/2/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 7/11/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 7/14/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/15/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 11/10/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/20/2023 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 12/1/2023 | Approved | RAUL BARAJAS |
| Final | 12/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/1/2023 | Approved | RAUL BARAJAS |
| Green Building Final | 12/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 12/1/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/1/2023 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 12/1/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | RAUL BARAJAS |
| Final | 12/8/2023 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 12/8/2023 | Approved | RAUL BARAJAS |