2710-2712 S WESTGATE AVE 90064
Certificate Information: 2710-2712 S WESTGATE AVE 90064
- Application / Permit
- 19014-30000-03513
- Plan Check / Job No.
- B19WL03681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Proposed attached ADU at rear of (E) SFD per AB494 &SB229.
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Current Status
- Issued on 10/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/3/2019 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 6/18/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 7/7/2020 | MANUEL GARCIA |
| Issued | 10/6/2020 | APPLICANT |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2019 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/9/2019 | DENNIS BRAGIN |
| Construction near power lines | Cleared | 9/19/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/3/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/5/2020 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Williamson Vincent Construction Inc; Lic. No.: 1050555-B | 8723 BLERIOT AVE LOS ANGELES, CA 90045 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 10/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 10/13/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/16/2020 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 10/29/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/2/2020 | Approved | OGANES TARAKHCHYAN |
| Sewer | 11/2/2020 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/23/2020 | Corrections Issued | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Approved | RICHARD ROBLES |
| Gas Test | 12/23/2020 | Approved | RICHARD ROBLES |
| Green Building Rough | 12/23/2020 | Corrections Issued | RICHARD ROBLES |
| HVAC-Rough | 12/23/2020 | Corrections Issued | RICHARD ROBLES |
| PLUMBING-Rough | 12/23/2020 | Approved | RICHARD ROBLES |
| BUILDING-Rough-Frame | 1/8/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/8/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 1/8/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/8/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/14/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/14/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/25/2021 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/27/2021 | Partial Approval | RICHARD ROBLES |
| Gas Test | 3/10/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/10/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/10/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 3/19/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 3/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 3/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/30/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |