8012 S READING AVE 90045
Certificate Information: 8012 S READING AVE 90045
- Application / Permit
- 19014-30000-03512
- Plan Check / Job No.
- B19WL03680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 story addition and interior alteration to (E) 1story SFD.
- Permit Issued
- Issued on 7/3/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Corrected on 1/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/1/2019 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 7/1/2019 | JASON JANGADA |
| Issued | 7/3/2019 | LADBS |
| CofO in Progress | 5/1/2020 | JUAN VALENZUELA |
| Building Plans Picked Up | 6/23/2020 | APPLICANT |
| CofO Issued-Status Void | 9/29/2020 | VINCENT COTTON |
| Permit Finaled-Status Void | 9/29/2020 | VINCENT COTTON |
| Re-Activate Permit | 11/16/2020 | VINCENT COTTON |
| CofO Corrected | 1/6/2021 | VINCENT COTTON |
| Permit Finaled | 1/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2019 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 7/1/2019 | CHINH DINH |
| Sewer availability | Cleared | 7/1/2019 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2019 | Approved | RONALD WEBER |
| BUILDING-Rough-Frame | 8/5/2019 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 8/5/2019 | Partial Approval | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 10/4/2019 | Corrections Issued | JUAN VALENZUELA |
| Shower Pan | 10/18/2019 | Conditional Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/24/2019 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/5/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 11/5/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/5/2019 | Approved | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 11/5/2019 | Approved | JUAN VALENZUELA |
| Insulation | 11/8/2019 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 11/13/2019 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/27/2020 | Approved | JUAN VALENZUELA |
| Final | 4/27/2020 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/27/2020 | Approved | JUAN VALENZUELA |
| Green Building Final | 4/27/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 4/27/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/27/2020 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 4/27/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/1/2020 | Approved | JUAN VALENZUELA |
| Final | 5/1/2020 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 5/1/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/1/2020 | Approved | JUAN VALENZUELA |