8012 S READING AVE 90045

Certificate Information: 8012 S READING AVE 90045

Application / Permit
19014-30000-03512
Plan Check / Job No.
B19WL03680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition and interior alteration to (E) 1story SFD.
Permit Issued
Issued on 7/3/2019
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 1/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/1/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 7/1/2019 VLADIMIR ARUTYUNYAN
Plan Check Approved 7/1/2019 JASON JANGADA
Issued 7/3/2019 LADBS
CofO in Progress 5/1/2020 JUAN VALENZUELA
Building Plans Picked Up 6/23/2020 APPLICANT
CofO Issued-Status Void 9/29/2020 VINCENT COTTON
Permit Finaled-Status Void 9/29/2020 VINCENT COTTON
Re-Activate Permit 11/16/2020 VINCENT COTTON
CofO Corrected 1/6/2021 VINCENT COTTON
Permit Finaled 1/6/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2019 CHINH DINH
Roof/Waste drainage to street Cleared 7/1/2019 CHINH DINH
Sewer availability Cleared 7/1/2019 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2019 Approved RONALD WEBER
BUILDING-Rough-Frame 8/5/2019 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 8/5/2019 Partial Approval JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 10/4/2019 Corrections Issued JUAN VALENZUELA
Shower Pan 10/18/2019 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 10/24/2019 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 11/5/2019 Approved JUAN VALENZUELA
Green Building Rough 11/5/2019 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 11/5/2019 Approved JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 11/5/2019 Approved JUAN VALENZUELA
Insulation 11/8/2019 Approved JUAN VALENZUELA
Drywall Nailing 11/13/2019 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/27/2020 Approved JUAN VALENZUELA
Final 4/27/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 4/27/2020 Approved JUAN VALENZUELA
Green Building Final 4/27/2020 Approved JUAN VALENZUELA
Green Building Rough 4/27/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/27/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 4/27/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 5/1/2020 Approved JUAN VALENZUELA
Final 5/1/2020 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 5/1/2020 Approved JUAN VALENZUELA
PLUMBING-Final 5/1/2020 Approved JUAN VALENZUELA