526 N BELLAGIO TER 90049
Certificate Information: 526 N BELLAGIO TER 90049
- Application / Permit
- 19014-30000-03491
- Plan Check / Job No.
- B19WL03664
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Remodel (E) single family dwelling. Per engineered design.
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2019 | ALFREDO JARA |
| Corrections Issued | 7/5/2019 | ALFREDO JARA |
| Applicant returned to address corrections | 5/29/2020 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 6/3/2020 | JASON JANGADA |
| Applicant returned to address corrections | 7/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/24/2020 | ALFREDO JARA |
| Plan Check Approved | 9/30/2020 | ALFREDO JARA |
| Issued | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 11/17/2020 | APPLICANT |
| CofO in Progress | 5/4/2022 | CARLOS MATAMOROS |
| CofO in Progress | 5/5/2022 | CARLOS MATAMOROS |
| CofO Issued | 5/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/23/2019 | OSCAR CASTRO |
| ZA Case | Cleared | 6/30/2020 | JOE LUCKEY |
| ZA Case | Cleared | 6/30/2020 | JOE LUCKEY |
| ZA Case | Cleared | 6/30/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/1/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 9/30/2020 | ALFREDO JARA |
Contact Information
| Contractor | J D Group Inc; Lic. No.: 675485-B | 1537 PONTIUS AVENUE SUITE B LOS ANGELES, CA 90025 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/24/2021 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/28/2021 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 6/29/2021 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 7/6/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 7/14/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 7/14/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Approved | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 7/30/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/10/2021 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/10/2021 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/10/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 8/26/2021 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 8/31/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 9/3/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/17/2021 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 10/5/2021 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/18/2021 | Approved | CARLOS MATAMOROS |
| Final | 10/18/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/18/2021 | Approved | CARLOS MATAMOROS |
| Green Building Final | 10/18/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/18/2021 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 10/18/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/18/2021 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 10/25/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/21/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 1/21/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/21/2022 | Approved | CARLOS MATAMOROS |
| Final | 4/27/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 4/27/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 4/27/2022 | Corrections Issued | CARLOS MATAMOROS |
| Final | 5/4/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/4/2022 | Approved | CARLOS MATAMOROS |