526 N BELLAGIO TER 90049

Certificate Information: 526 N BELLAGIO TER 90049

Application / Permit
19014-30000-03491
Plan Check / Job No.
B19WL03664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Remodel (E) single family dwelling. Per engineered design.
Permit Issued
Issued on 10/5/2020
Issuing Office
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2019 APPLICANT
Assigned to Plan Check Engineer 7/2/2019 ALFREDO JARA
Corrections Issued 7/5/2019 ALFREDO JARA
Applicant returned to address corrections 5/29/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 6/3/2020 JASON JANGADA
Applicant returned to address corrections 7/28/2020 PARISA ZAHABI
Applicant returned to address corrections 9/24/2020 ALFREDO JARA
Plan Check Approved 9/30/2020 ALFREDO JARA
Issued 10/5/2020 APPLICANT
Building Plans Picked Up 11/17/2020 APPLICANT
CofO in Progress 5/4/2022 CARLOS MATAMOROS
CofO in Progress 5/5/2022 CARLOS MATAMOROS
CofO Issued 5/7/2022 DANIEL ORRANTE
Permit Finaled 5/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 9/23/2019 OSCAR CASTRO
ZA Case Cleared 6/30/2020 JOE LUCKEY
ZA Case Cleared 6/30/2020 JOE LUCKEY
ZA Case Cleared 6/30/2020 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 7/1/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 7/1/2020 DINAH GARIN
Grading Pre-Inspection Cleared 9/30/2020 ALFREDO JARA

Contact Information

Contractor J D Group Inc; Lic. No.: 675485-B 1537 PONTIUS AVENUE SUITE B      LOS ANGELES, CA 90025

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/24/2021 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/28/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval CARLOS MATAMOROS
Wood Frame 6/29/2021 Partial Approval CARLOS MATAMOROS
Service/Power Release 7/6/2021 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 7/14/2021 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 7/14/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Approved CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 7/30/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/10/2021 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Approved CARLOS MATAMOROS
Green Building Rough 8/10/2021 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 8/10/2021 Not Ready for Inspection CARLOS MATAMOROS
Insulation 8/26/2021 Approved JESUS RODRIGUEZ
Drywall Nailing 8/31/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 9/3/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 9/17/2021 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 10/5/2021 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 10/18/2021 Approved CARLOS MATAMOROS
Final 10/18/2021 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 10/18/2021 Approved CARLOS MATAMOROS
Green Building Final 10/18/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 10/18/2021 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/18/2021 Approved CARLOS MATAMOROS
Structural Steel Frame 10/25/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/21/2022 Approved CARLOS MATAMOROS
HVAC-Final 1/21/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 1/21/2022 Approved CARLOS MATAMOROS
Final 4/27/2022 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 4/27/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 4/27/2022 Corrections Issued CARLOS MATAMOROS
Final 5/4/2022 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 5/4/2022 Approved CARLOS MATAMOROS