335 S BRISTOL AVE 90049
Certificate Information: 335 S BRISTOL AVE 90049
- Application / Permit
- 19014-30000-03432
- Plan Check / Job No.
- B19WL03596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2019 | APPLICANT |
| Green Plans Picked Up | 7/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | REZA HAGHIGHAT |
| Corrections Issued | 7/22/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 7/30/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Applicant returned to address corrections | 8/28/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 10/2/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/15/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/16/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 2/19/2020 | REZA HAGHIGHAT |
| Issued | 6/19/2020 | LADBS |
| CofO in Progress | 10/1/2024 | JESUS RODRIGUEZ |
| CofO Issued | 10/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/17/2019 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 11/25/2019 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 11/25/2019 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 11/25/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 11/25/2019 | EMIL KYUPELYAN |
| ZA Case | Cleared | 11/25/2019 | SOPHIE GABEL-SCHEINBAU |
| GPI Written Notices | Cleared | 12/16/2019 | REZA HAGHIGHAT |
| Green Code | Cleared | 2/27/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Mp Monte Construction Inc; Lic. No.: 979730-B | 888 S FIGUEROA STREET #650 LOS ANGELES, CA 90017 |
| Engineer | Naim,, Soleiman Israel; Lic. No.: S2454 | 403 21ST ST SANTA MONICA, CA 90402 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/20/2020 | Conditional Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2020 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 9/17/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/5/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/14/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/14/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/14/2021 | Approved | JOHN KIDWELL |
| HVAC-Rough | 1/14/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 1/14/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 2/2/2021 | Approved | JOHN KIDWELL |
| Pre-Inspection | 3/24/2021 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/4/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 8/4/2021 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 12/22/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/10/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/31/2022 | Approved | KEVIN SARGSYAN |
| Green Building Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 10/31/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 10/31/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Structural Steel Frame | 10/31/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/29/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 9/19/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Final | 9/19/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/19/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 9/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/30/2024 | Approved | JESUS RODRIGUEZ |
| Final | 9/30/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Smoke Detectors | 9/30/2024 | Approved | JESUS RODRIGUEZ |