761 N ILIFF ST 90272

Certificate Information: 761 N ILIFF ST 90272

Application / Permit
19014-30000-03290
Plan Check / Job No.
B19WL03430
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of (E) garage to an accessory dwelling unit (ADU) per AB 494 and SB 229. Per engineering design.
Permit Issued
Issued on 1/7/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2019 APPLICANT
Assigned to Plan Check Engineer 6/26/2019 ALFREDO JARA
Corrections Issued 6/28/2019 ALFREDO JARA
Building Plans Picked Up 7/8/2019 APPLICANT
Applicant returned to address corrections 8/15/2019 REZA HAGHIGHAT
Plan Check Approved 9/11/2019 REZA HAGHIGHAT
Issued 1/7/2020 LADBS
CofO in Progress 5/21/2021 JOHN KIDWELL
CofO Issued 7/14/2021 VINCENT COTTON
Permit Finaled 7/14/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 7/16/2019 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 7/16/2019 MAHELET GEBEYHU
Sewer availability Cleared 7/26/2019 STEVEN JIN
Low Impact Development Cleared 8/15/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/15/2019 CELINA MORENO
Grading Pre-Inspection Cleared 8/16/2019 BRIAN OLSON
Construction near power lines Cleared 9/3/2019 RIDWAN HARDY

Contact Information

Contractor Kanan Construction; Lic. No.: 554451-B 1531 15TH STREET #1      SANTA MONICA, CA 90404
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/5/2020 Conditional Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/28/2020 Not Ready for Inspection DANNY TOLENTINO
Gas Test 3/20/2020 Partial Approval ROBERT SHELLY
PLUMBING-Rough 3/20/2020 Not Ready for Inspection ROBERT SHELLY
Sewer 3/20/2020 Partial Approval ROBERT SHELLY
Underground Mechanical 3/20/2020 Approved ROBERT SHELLY
Footing/Foundation/Slab 3/26/2020 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 6/24/2020 Approved ROBERT SHELLY
ELECTRICAL-Rough 6/24/2020 Approved ROBERT SHELLY
Gas Test 6/24/2020 Approved ROBERT SHELLY
Green Building Rough 6/24/2020 Approved ROBERT SHELLY
HVAC-Rough 6/24/2020 Approved ROBERT SHELLY
PLUMBING-Rough 6/24/2020 Approved ROBERT SHELLY
Wood Frame 6/24/2020 Approved ROBERT SHELLY
Insulation 7/7/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/7/2020 Partial Approval JOHN KIDWELL
Shower Pan 7/7/2020 Approved JOHN KIDWELL
Drywall Nailing 7/14/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/14/2020 Partial Approval JOHN KIDWELL
Gas Test 9/2/2020 Approved JOHN KIDWELL
Service/Power Release 9/2/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 4/1/2021 Approved JOHN KIDWELL
Final 4/1/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 4/1/2021 Approved JOHN KIDWELL
Green Building Final 4/1/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 4/1/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 4/1/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/1/2021 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 4/1/2021 Approved JOHN KIDWELL
ELECTRICAL-Final 5/20/2021 Approved JOHN KIDWELL
Final 5/20/2021 OK to Issue CofO JOHN KIDWELL
Green Building Final 5/20/2021 Approved JOHN KIDWELL
HVAC-Final 5/20/2021 Approved JOHN KIDWELL
PLUMBING-Final 5/20/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Approved JOHN KIDWELL