3351 N DERONDA DR 90068
Certificate Information: 3351 N DERONDA DR 90068
- Application / Permit
- 19014-30000-03147
- Plan Check / Job No.
- B19WL03272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and alteration to existing 2 story dwelling. (SEE COMMENT)
- Permit Issued
- Issued on 3/3/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/8/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/10/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 7/15/2019 | APPLICANT |
| Applicant returned to address corrections | 8/20/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/30/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 11/6/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/3/2021 | APPLICANT |
| Building Plans Picked Up | 3/18/2021 | APPLICANT |
| CofO in Progress | 1/25/2023 | STUART CHAPMAN |
| Permit Finaled | 2/9/2023 | DEROLD HAUFF |
| CofO Issued | 2/9/2023 | DEROLD HAUFF |
| Permit Finaled | 2/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2019 | TAO YANG |
| Roof/Waste drainage to street | Cleared | 8/20/2019 | TAO YANG |
Contact Information
| Contractor | Perkins Michael Construction; Lic. No.: 745473-B | 520 S SUNSET CANYON DRIVE BURBANK, CA 91501 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Niaki,, Neman; Lic. No.: C46030 | 1107 CALIFORNIA AVE #2 SANTA MONICA, CA 90403 |
| Geologist | Byer,, John W; Lic. No.: EG883 | 1649 PUEBLA DRIVE GLENDALE, CA 91207 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/9/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 8/9/2021 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/20/2021 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/20/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 8/20/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 8/20/2021 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/20/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 9/20/2021 | Partial Inspection | ROBERT VORHIS |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Rough | 9/20/2021 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Rough | 9/20/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 10/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 10/6/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/6/2021 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 10/6/2021 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/16/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 12/16/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 12/16/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/16/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 12/16/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/21/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 12/21/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 12/21/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/28/2021 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 12/28/2021 | Not Ready for Inspection | JOSE AVILA |
| Drywall Nailing | 12/30/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/5/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 1/19/2022 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 5/16/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/26/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/26/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 10/3/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 12/1/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 12/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 12/1/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 12/1/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 12/1/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 12/1/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 12/22/2022 | OK for TCO | STUART CHAPMAN |
| Final | 1/25/2023 | OK to Issue CofO | STUART CHAPMAN |