381 N LAS CASAS AVE 90272
Certificate Information: 381 N LAS CASAS AVE 90272
- Application / Permit
- 19014-30000-03119
- Plan Check / Job No.
- B19WL03233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story SFD MAJOR REMODEL AND ADDITION KEEPING ONLY 2-FT OF WALL.
- Permit Issued
- Issued on 8/5/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2019 | APPLICANT |
| Green Plans Picked Up | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | TARIK SAOUD |
| Corrections Issued | 7/8/2019 | TARIK SAOUD |
| Quality Review Completed | 7/10/2019 | FELIX FIGUEROA |
| Plan Check Approved | 8/5/2019 | TARIK SAOUD |
| Issued | 8/5/2019 | LADBS |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| CofO in Progress | 6/4/2021 | ANDREW NAVE |
| Permit Finaled | 6/30/2021 | KENNETH NAGLE |
| CofO Issued | 6/30/2021 | KENNETH NAGLE |
| Permit Finaled | 6/30/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 7/12/2019 | TREVOR MARTIN |
| Hydrant and Access approval | Cleared | 7/16/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 7/16/2019 | RYAN HUDSON |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2019 | DENNIS BRAGIN |
| Green Code | Cleared | 7/18/2019 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 7/18/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/18/2019 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 8/5/2019 | TARIK SAOUD |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2019 | Partial Inspection | MICHAEL TEMPLE |
| Deputy Drilled-In Anchors | 6/5/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/10/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 7/1/2020 | Partial Approval | ANDREW NAVE |
| Wood Frame | 7/7/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Corrections Issued | ANDREW NAVE |
| Deputy Other (see comments) | 7/16/2020 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/5/2020 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Inspection | ANDREW NAVE |
| Deputy Wood Construction | 8/6/2020 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 12/22/2020 | Approved | KENNETH NAGLE |
| Deputy Wood Construction | 1/13/2021 | Conditional Approval | ANDREW NAVE |
| Insulation | 1/13/2021 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 1/15/2021 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 1/22/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 1/25/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/28/2021 | Partial Inspection | ANDREW NAVE |
| Deputy Wood Construction | 1/28/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 1/28/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 1/28/2021 | Partial Approval | ANDREW NAVE |
| Shower Pan | 1/28/2021 | Approved | ANDREW NAVE |
| Insulation | 2/1/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 2/10/2021 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 2/10/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 5/3/2021 | Corrections Issued | ANDREW NAVE |
| Gas Test | 5/4/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 5/4/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 5/4/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 5/12/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 5/14/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/14/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | ANDREW NAVE |
| Final | 5/21/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 5/21/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 5/21/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 5/21/2021 | Approved | ANDREW NAVE |
| Green Building Final | 5/26/2021 | Approved | ANDREW NAVE |
| Final | 6/4/2021 | OK to Issue CofO | ANDREW NAVE |
| Service/Power Release | 6/4/2021 | Approved | ANDREW NAVE |