617 W VICTORIA AVE 90291
Certificate Information: 617 W VICTORIA AVE 90291
- Application / Permit
- 19014-30000-02919
- Plan Check / Job No.
- B19WL03060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2-STORY ADDITION WITH ROOF DECK TO EXISTING 1-STORY TYPE VB DUPLEX WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 4/2/2020
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | SERGIO SILVA |
| Green Plans Picked Up | 7/10/2019 | APPLICANT |
| Corrections Issued | 7/23/2019 | SERGIO SILVA |
| Quality Review Completed | 8/2/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 8/22/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 2/14/2020 | SERGIO SILVA |
| Plan Check Approved | 3/26/2020 | SERGIO SILVA |
| Issued | 4/2/2020 | APPLICANT |
| Building Plans Picked Up | 4/3/2020 | APPLICANT |
| CofO in Progress | 7/21/2022 | RICHARD STEINBACH |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
| CofO Issued | 7/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 12/10/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 12/10/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 12/10/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 12/10/2019 | STEVEN WECHSLER |
| Permit | Cleared | 12/11/2019 | DINAH GARIN |
| Sewer availability | Cleared | 12/11/2019 | DINAH GARIN |
| Trees in Parkway | Cleared | 1/23/2020 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 1/24/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 1/28/2020 | RICHARD GARCIA |
| Coastal Zone | Cleared | 2/13/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 2/13/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 2/13/2020 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 3/16/2020 | ANDRES COVARRUBIAS |
| GPI Written Notices | Cleared | 3/17/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 3/17/2020 | SERGIO SILVA |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | DINAH GARIN |
| Specific Plan | Cleared | 3/18/2020 | FREDDY GARCIA |
| Specific Plan | Cleared | 3/18/2020 | FREDDY GARCIA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/11/2020 | Conditional Approval | DAVID FEILER |
| Pre-Inspection | 5/13/2020 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 5/20/2020 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 5/20/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 5/20/2020 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 5/21/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 5/22/2020 | Partial Approval | DAVID HEINE |
| Insulation | 5/28/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 6/2/2020 | Partial Approval | DAVID HEINE |
| Deputy Steel/Welding | 7/1/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 7/10/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 7/10/2020 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | DAVID HEINE |
| Insulation | 11/10/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 11/10/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 11/16/2020 | Partial Approval | ENRIQUE MIRELES |
| Insulation | 11/18/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/18/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Shower Pan | 11/20/2020 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 12/1/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/4/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/9/2020 | Corrections Issued | JOHNNY MIRANDA |
| Shower Pan | 12/9/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/14/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/22/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/22/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/28/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 1/5/2021 | Approved | PIERRE VEGA |
| Drywall Nailing | 1/26/2021 | Approved | ENRIQUE MIRELES |
| Final | 4/6/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/6/2022 | Approved | PATRICK QUALEY |
| Green Building Final | 4/6/2022 | Approved | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | PATRICK QUALEY |
| Smoke Detectors | 4/6/2022 | Approved | PATRICK QUALEY |
| Final | 4/20/2022 | Corrections Issued | PATRICK QUALEY |
| Final | 7/19/2022 | Conditional Approval | PATRICK QUALEY |