1409 S MIDVALE AVE 1-58 90024

Certificate Information: 1409 S MIDVALE AVE 1-58 90024

Application / Permit
19014-30000-02758
Plan Check / Job No.
B19WL02914
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert (e) lobby area to a new studio apartment unit w/ a bathroom and kitchen resulting in total of 59 unit apartment
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2019 APPLICANT
Disabled Access Plans Picked Up 6/10/2019 APPLICANT
Green Plans Picked Up 6/11/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 MARJAN SHENASI
Corrections Issued 6/17/2019 MARJAN SHENASI
Quality Review Completed 6/25/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/25/2019 APPLICANT
Plan Check Approved 6/28/2021 MARJAN SHENASI
Issued 10/15/2021 APPLICANT
CofO in Progress 7/13/2023 PAUL DAVIDSON
Permit Finaled 7/24/2023 DAVID TSAU
CofO Issued 7/24/2023 DAVID TSAU
Permit Finaled 7/24/2023 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 6/27/2019 TAO YANG
Eng Process Fee Ord 176,300 Cleared 6/27/2019 TAO YANG
Miscellaneous Cleared 6/27/2019 NOAH MCCOY
Miscellaneous Cleared 6/27/2019 NOAH MCCOY
Miscellaneous Cleared 6/27/2019 NOAH MCCOY
Sewer availability Cleared 6/27/2019 TAO YANG
DAS Clearance Cleared 9/13/2019 SOMKIAT SUPANYACHOTSKUL
Green Code Cleared 9/19/2019 DONALD CRICHLOW
Specific Plan Cleared 9/25/2019 VALERIA CEJA
Fire Marshall Fire Life Safety Cleared 1/26/2021 OSCAR SALGADO JR
"Q" conditions Cleared 4/7/2021 MINDY NGUYEN
Specific Plan Cleared 4/7/2021 MINDY NGUYEN

Contact Information

Architect Newlove,, Victor M; Lic. No.: C5570 1330 OLYMPIC BLVD      SANTA MONICA, CA 90404
Contractor Electron Electric Inc; Lic. No.: 541980-B 2846 COLORADO AVE      SANTA MONICA, CA 904043637

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/13/2021 Corrections Issued JOHN DODGE
Insulation 12/30/2021 Partial Inspection PAUL DAVIDSON
Pre-Inspection 12/30/2021 Partial Approval PAUL DAVIDSON
Smoke Detectors 12/30/2021 Not Ready for Inspection PAUL DAVIDSON
Final 3/3/2022 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 3/3/2022 Approved PAUL DAVIDSON
Green Building Final 3/3/2022 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 3/3/2022 Approved PAUL DAVIDSON
METHANE-Barrier 3/3/2022 Approved PAUL DAVIDSON
METHANE-Final 3/3/2022 Approved PAUL DAVIDSON
METHANE-Rough 3/3/2022 Approved PAUL DAVIDSON
METHANE-Subgrade 3/3/2022 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 3/3/2022 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 3/3/2022 Approved PAUL DAVIDSON
Final 3/15/2022 Corrections Issued PAUL DAVIDSON
Green Building Final 3/15/2022 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 3/15/2022 Not Ready for Inspection PAUL DAVIDSON
Final 4/14/2022 Not Ready for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 4/14/2022 Approved PAUL DAVIDSON
Final 4/14/2023 Not Ready for Inspection PAUL DAVIDSON
Final 7/6/2023 Conditional Approval MICHAEL PETRUSKO