180 S GARDNER ST 90036

Certificate Information: 180 S GARDNER ST 90036

Application / Permit
19014-30000-02578
Plan Check / Job No.
B19WL02717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD, REMODEL (E) KITCHEN/BATHROOMS, AND REPLACE (E) WINDOWS/DOORS
Permit Issued
Issued on 7/29/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2019 APPLICANT
Assigned to Plan Check Engineer 5/22/2019 REZA HAGHIGHAT
Corrections Issued 5/22/2019 REZA HAGHIGHAT
Building Plans Picked Up 5/24/2019 APPLICANT
Applicant returned to address corrections 7/22/2019 REZA HAGHIGHAT
Plan Check Approved 7/25/2019 REZA HAGHIGHAT
Issued 7/29/2019 LADBS
CofO in Progress 12/15/2022 MICHAEL LEWIS
Permit Finaled 12/17/2022 DEROLD HAUFF
CofO Issued 12/17/2022 DEROLD HAUFF
Permit Finaled 12/17/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 7/19/2019 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 7/19/2019 JEANETTE VONG
HPOZ Cleared 7/19/2019 MICAELA TORRES-GIL
Low Impact Development Cleared 7/19/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/19/2019 JEANETTE VONG
Sewer availability Cleared 7/19/2019 JEANETTE VONG
ZA Case Cleared 7/19/2019 MICAELA TORRES-GIL
ZI Cleared 7/19/2019 MICAELA TORRES-GIL

Contact Information

Architect Getov,, Pavel Panayotov; Lic. No.: C32093 3565 REDWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Mina,, Joseph Wadie; Lic. No.: C53465 7247 DARNOCH WY      WEST HILLS, CA 91307

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/18/2019 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 9/18/2019 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 9/18/2019 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 9/24/2019 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/24/2019 Corrections Issued JOSEPH MCGARRY
HVAC-Rough 9/24/2019 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 9/24/2019 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 9/24/2019 Approved CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 10/2/2019 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 3/2/2020 Approved RICHARD STEINBACH
HVAC-Rough 3/2/2020 Not Ready for Inspection RICHARD STEINBACH
BUILDING-Rough-Frame 3/19/2020 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 3/19/2020 Corrections Issued BRAD BESCOS
Green Building Rough 3/19/2020 Not Ready for Inspection BRAD BESCOS
HVAC-Rough 3/19/2020 Not Ready for Inspection BRAD BESCOS
METHANE-Barrier 3/19/2020 Not Ready for Inspection BRAD BESCOS
METHANE-Rough 3/19/2020 Not Ready for Inspection BRAD BESCOS
METHANE-Subgrade 3/19/2020 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 4/22/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 4/22/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 4/22/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/29/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/29/2020 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 4/29/2020 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 9/16/2020 Corrections Issued CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 10/1/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/8/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 10/8/2020 Approved CHRIS CHRISTENSEN
Insulation 10/8/2020 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 10/8/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/16/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/20/2020 Partial Approval CHRIS CHRISTENSEN
Final 10/6/2022 Corrections Issued MICHAEL LEWIS
Green Building Final 10/6/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 10/6/2022 Corrections Issued MICHAEL LEWIS
Final 10/31/2022 Corrections Issued MICHAEL LEWIS
Smoke Detectors 10/31/2022 Approved MICHAEL LEWIS
Final 11/14/2022 Not Ready for Inspection JOSEPH MCGARRY
Final 12/8/2022 OK to Issue CofO MICHAEL LEWIS