155 S GREENFIELD AVE 90049

Certificate Information: 155 S GREENFIELD AVE 90049

Application / Permit
19014-30000-02523
Plan Check / Job No.
B19WL02656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior alteration & 2nd story addition to (E) 1 story SFD.
Permit Issued
Issued on 8/15/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 6/4/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 6/13/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/13/2019 APPLICANT
Building Plans Picked Up 6/14/2019 APPLICANT
Plan Check Approved 8/15/2019 VLADIMIR ARUTYUNYAN
Issued 8/15/2019 LADBS
CofO in Progress 3/2/2021 CARLOS MATAMOROS
CofO Issued 3/15/2021 VINCENT COTTON
Permit Finaled 3/15/2021 VINCENT COTTON

Permit Application Clearance Information

Low Impact Development Cleared 7/19/2019 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 7/22/2019 KARAN PATEL
Roof/Waste drainage to street Cleared 7/22/2019 KARAN PATEL
Sewer availability Cleared 7/22/2019 KARAN PATEL
Green Code Cleared 8/6/2019 RICHARD GARCIA
GPI Written Notices Cleared 8/9/2019 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 8/9/2019 VLADIMIR ARUTYUNYAN

Contact Information

Architect Naraghi,, Homay M; Lic. No.: C17555 8500 WILSHIRE BLVD # 826      BEVERLY HILLS, CA 90211
Contractor Escobar Edgar A; Lic. No.: 860516-B 8201 4TH STREET STE B      DOWNEY, CA 90241
Engineer Minn,, Wen-Chung; Lic. No.: C42605 3358 W 157TH ST      GARDENA, CA 90249

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/27/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 10/1/2019 Approved TIM CHRISTENSEN
Deputy Wood Construction 10/2/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Wood Construction 3/25/2020 Conditional Approval TIM CHRISTENSEN
BUILDING-Rough-Frame 5/13/2020 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 5/13/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 5/13/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 5/13/2020 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 5/13/2020 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 5/21/2020 Approved CARLOS MATAMOROS
Gas Test 5/21/2020 Approved CARLOS MATAMOROS
Green Building Rough 5/21/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 5/21/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 5/22/2020 Corrections Issued CARLOS MATAMOROS
Gas Test 5/22/2020 Approved CARLOS MATAMOROS
HVAC-Rough 5/22/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 6/2/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 6/2/2020 Approved CARLOS MATAMOROS
Shower Pan 6/2/2020 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/4/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Approved CARLOS MATAMOROS
HVAC-Rough 6/4/2020 Approved CARLOS MATAMOROS
Insulation 6/16/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/16/2020 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 6/18/2020 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 6/19/2020 Approved CARLOS MATAMOROS
Drywall Nailing 6/23/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/2/2020 Approved CARLOS MATAMOROS
Final 10/15/2020 Corrections Issued CARLOS MATAMOROS
Green Building Final 10/15/2020 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 10/15/2020 Approved CARLOS MATAMOROS
Gas Test 10/26/2020 Approved TIM CHRISTENSEN
ELECTRICAL-Final 11/9/2020 Approved CARLOS MATAMOROS
Final 11/9/2020 Corrections Issued CARLOS MATAMOROS
Green Building Final 11/9/2020 Approved CARLOS MATAMOROS
HVAC-Final 11/9/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 11/9/2020 Approved CARLOS MATAMOROS
HVAC-Final 12/16/2020 Approved CARLOS MATAMOROS
PLUMBING-Final 12/16/2020 Approved CARLOS MATAMOROS
Final 3/2/2021 OK to Issue CofO CARLOS MATAMOROS