2344 N BANYAN DR 90049
Certificate Information: 2344 N BANYAN DR 90049
- Application / Permit
- 19014-30000-02496
- Plan Check / Job No.
- B19WL02627
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION AND REMODEL TO (E) 2-STORY SFD W/ ATT. GARAGE. DEMOLISH (E) ATT. TRELLIS AT REAR SIDE OF THE BLDG.
- Permit Issued
- Issued on 8/30/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Green Plans Picked Up | 5/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | REZA HAGHIGHAT |
| Corrections Issued | 6/3/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 6/14/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/14/2019 | APPLICANT |
| Applicant returned to address corrections | 7/5/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 8/1/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 8/19/2019 | REZA HAGHIGHAT |
| Issued | 8/30/2019 | LADBS |
| CofO in Progress | 10/28/2021 | JUAN VALENZUELA |
| Permit Finaled | 11/17/2021 | DANIEL ORRANTE |
| CofO Issued | 11/17/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/17/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/5/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 7/5/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 7/5/2019 | JOSE CRUZ RODRIGUEZ |
| GPI Written Notices | Cleared | 7/5/2019 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 7/5/2019 | REZA HAGHIGHAT |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | CHRISTOPHER LAW |
| Flood clearance | Cleared | 7/29/2019 | OSCAR GUTIERREZ |
| Low Impact Development | Cleared | 7/29/2019 | JORGE MEJIA LEMUS |
| Sewer availability | Cleared | 7/29/2019 | CHRISTOPHER LAW |
| Green Code | Cleared | 7/31/2019 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 8/1/2019 | JOSE CRUZ RODRIGUEZ |
| Watercourse | Cleared | 8/1/2019 | JOSE CRUZ RODRIGUEZ |
| Hydrant and Access approval | Cleared | 8/5/2019 | ROBERT DUFF |
| Miscellaneous | Cleared | 8/6/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 8/6/2019 | SARAH GOLDMAN |
Contact Information
| Contractor | Crane Steven & Co Inc; Lic. No.: 667129-B | 2959 SEPULVEDA BLVD LOS ANGELES, CA 90064 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Partial Approval | TIM CHRISTENSEN |
| Piling/Pier/Caisson | 3/27/2020 | Partial Approval | ROBERT SHELLY |
| FLOOD-Elevation Certificate | 4/16/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/16/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/17/2020 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/21/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/10/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 6/10/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 6/15/2020 | Partial Approval | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 6/23/2020 | Approved | ROBERT SHELLY |
| FLOOD-Proofing Certificate | 6/23/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Green Building Rough | 6/23/2020 | Not Ready for Inspection | ROBERT SHELLY |
| HVAC-Rough | 6/23/2020 | Approved | ROBERT SHELLY |
| FLOOD-Proofing Certificate | 7/2/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Conditional Approval | TIM CHRISTENSEN |
| Green Building Rough | 7/2/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 7/2/2020 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 7/17/2020 | Conditional Approval | TIM CHRISTENSEN |
| FLOOD-Proofing Certificate | 7/17/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Green Building Rough | 7/17/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 7/24/2020 | Approved | TIM CHRISTENSEN |
| FLOOD-Proofing Certificate | 7/24/2020 | Approved | TIM CHRISTENSEN |
| Green Building Rough | 7/24/2020 | Approved | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 7/24/2020 | Approved | TIM CHRISTENSEN |
| Insulation | 7/29/2020 | Approved | TIM CHRISTENSEN |
| Drywall Nailing | 8/7/2020 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 2/23/2021 | Corrections Issued | ROBERT SHELLY |
| Final | 9/16/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/16/2021 | Approved | JUAN VALENZUELA |
| Green Building Final | 9/16/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 9/16/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 10/8/2021 | Approved | JUAN VALENZUELA |
| Final | 10/8/2021 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 10/8/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 10/8/2021 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 10/8/2021 | Approved | JUAN VALENZUELA |